Inspection Status: Re-inspection required
Inspection History: COT - LCPL - Rough Soil
| Date |
Description |
Inspector |
Results |
Comments |
| 04/15/2026 |
COT - LCPL - Rough Soil |
|
Re-inspection required |
4-15-26: called point of contact at 715am but did not receive an answer. Arrived on site at 719am-noted that gate was locked. Left site after waiting 10 minutes. Reschedule at your convenience. |
| 04/16/2026 |
COT - LCPL - Rough Soil |
|
Re-inspection required |
4-16-26: underground plumbing is not installed per approved plans. Either install per plans or submit a revision to the city for review. See Page P1.0, plumbing schedule P2 (lavatory) must extend out the south wall where it connects to the sewer. P2 will also require a vent. P3 & P1 extend out the east wall where it too connects the 3" sewer. P3 & P6 were not under test. The underground plumbing test requires a 10' water head & shall be under test for 24 hours-see plumbing notes for information. |
| 05/05/2026 |
COT - LCPL - Rough Soil |
|
Partial Pass |
5/5/2026 all corrections were made. Okay to backfill progress areas. Pending tie into main. |
| 07/14/2026 |
COT - LCPL - Rough Soil |
|
Re-inspection required |
7-14-26: missing tracer wire at tie-in. |
| 07/21/2026 |
COT - LCPL - Rough Soil |
|
Passed |
7-21-26: tie in approved. Okay to backfill using shading materials. |