Inspection Status: Partial Pass
Inspection History: COT - CSOL - Electrical Underground Solar Project
| Date |
Description |
Inspector |
Results |
Comments |
| 02/05/2026 |
COT - CSOL - Electrical Underground Solar Project |
|
Partial Pass |
2/5/26: UFER APPROVED FOR CANOPY C. Reinforcement per approved plans at (3)spread footings for canopy C ok to proceed with concrete placement |
| 02/09/2026 |
COT - CSOL - Electrical Underground Solar Project |
|
Partial Pass |
|
| 02/11/2026 |
COT - CSOL - Electrical Underground Solar Project |
|
Partial Pass |
2/11/2026 New panel board location coming from canopy A. 3" x2 1". Schedule 40 at 48" depth. A to D X5 1" schedule 40 42" to top of pipe. Okay to backfill progress areas. Shading required. |
| 02/12/2026 |
COT - CSOL - Electrical Underground Solar Project |
|
Canceled |
Canceled per contractor. 2/12/2026 |
| 02/19/2026 |
COT - CSOL - Electrical Underground Solar Project |
|
Partial Pass |
Partial pass. Tie ins from previous inspection. New risers at canopy D. Okay to backfill progress areas. Shading required. 2/19/2026 |
| 03/09/2026 |
COT - CSOL - Electrical Underground Solar Project |
|
Passed |
Passed for final canopy 3/9/26 |