Inspection Status: Partial Pass
Inspection History: COT - LCBU - Excavation/Rebar/Zoning
| Date |
Description |
Inspector |
Results |
Comments |
| 02/05/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
2/5/26: UFER APPROVED FOR CANOPY C. Reinforcement per approved plans at (3)spread footings for canopy C ok to proceed with concrete placement |
| 02/06/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Canceled |
|
| 02/09/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
|
| 02/11/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
2/11/2026 total of 1 spread footer at canopy A. Okay for concrete placement. |
| 02/12/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
2/12/2026 1 spread footer at canopy A meter 1. Okay for concrete placement. |
| 02/19/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
2/19/2026 Meter 1. Total of 6 spread footings. Canopies D,E,&F. Okay for concrete placement. |
| 03/09/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Passed |
Passed for final canopy 3/9/26 |