Inspection History Details
Inspection Status: Not Ready
Inspection History: ENGR Engineering Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/07/2025 | ENGR Engineering Final | Not Ready | 8/7/25 Loading dock on bldg. 2701 is not to plan. Asphalt is at grade with Doors instead of well loading dock per plan. At opposite side of building new curb and asphalt has not been installed for truck access to new dock. East of bldg. 2721 there is unfinished electrical conduit sticking out of surface of parking lot area. Dumpsters and Portajohns still on site. |
|
| 08/27/2025 | ENGR Engineering Final | Passed |