Inspection History Details
Inspection Status: Re-inspection required
Inspection History: COT - LCBU - Building Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/27/2025 | COT - LCBU - Building Final | Re-inspection required | 8-27-25: pending conditions, required corrections to include: wrapping of hot piping on water heater, RFI for HVAC & RFI for receptacle relocation in office area, adjusting all interior /exit doors to open at 5 pounds of pressure, missing junction box lid at electrical room above ceiling,firefoam any vertical /horizontal penetration where piping/conduits extend through to another space. Existing electrical panels not in use must be "gutted" to the possible unlawful use at a later date and must be clearly labeled "panel not in use." | |
| 09/02/2025 | COT - LCBU - Building Final | Re-inspection required | 9-2-25: pending HVAC & electrical RFI, add blanks to panels not in use and install a permanent label on all panels not being used, firefoam all penetrations at outlined areas noted from previous notes. | |
| 09/05/2025 | COT - LCBU - Building Final | Partial Pass | 9-5-25: partial pass pending Air balance report, Electrical & HVAC RFI Okay for Level 4 TCO. |
|
| 09/09/2025 | COT - LCBU - Building Final | Passed | 9-9-25: Building final approved. Note: see pending conditions. |