Inspection Status: Partial Pass
Inspection History: COT - HCEL - Electrical Underground
| Date |
Description |
Inspector |
Results |
Comments |
| 06/20/2025 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
6/20/25: conduits for feeders from SES to MDP approved ok to backfill. secondaries stubbing out from building approved 20' run ok to backfill |
| 06/24/2025 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
6/24/2025. Partial pass. All in slab conduits approved. Okay to backfill progress areas. |
| 06/30/2025 |
COT - HCEL - Electrical Underground |
|
Partial Pass |
6/30/2025 1" scheduled 40 conduit at 2´ depth. Feeding a total of 4 light poles. X2 on south end other 2 are west end. |
| 07/24/2025 |
COT - HCEL - Electrical Underground |
|
Canceled |
7-24-25: inspection must be made by engineering. |
| 10/27/2025 |
COT - HCEL - Electrical Underground |
|
Passed |
|