Inspection Status: Not Ready
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 05/05/2025 |
ENGR Engineering Final
|
|
Not Ready |
This is more of a pre-con inspection to go over to see what he needed to do in the parking lot and some of the ramp areas and sidewalk areas |
| 06/13/2025 |
ENGR Engineering Final
|
|
Partial Pass |
Striping and ADA signage not done. Okay for level 1 TCO. |
| 07/09/2025 |
ENGR Engineering Final
|
|
Passed |
Okay for full C of O. As-Builts set of plans required prior to final closeout. Should these not be provided, C of O will be rescinded. See details in the checklist items. 7/9/25 Disregard earlier comment. Approved As-Built plan complies with current parking layout. ADA requirements met. |