Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Building Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 03/20/2025 |
COT - HCBU - Building Progress |
|
Partial Pass |
3-20-25, underground plumbing office area bathrooms on north side verified under test and per plans. Okay to backfill. |
| 05/02/2025 |
COT - HCBU - Building Progress |
|
Partial Pass |
|
| 08/27/2025 |
COT - HCBU - Building Progress |
|
Not Ready |
8-27-25: not ready. |
| 09/02/2025 |
COT - HCBU - Building Progress |
|
Passed |
9-2-25: approved. |