Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - HCBU - Building Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/27/2025 | COT - HCBU - Building Final | Not Ready | 8-27-25: not ready. | |
| 09/02/2025 | COT - HCBU - Building Final | Re-inspection required | 9-2-25: seal water closet and install wall mount paper dispenser. Pending HVAC RFI. | |
| 09/05/2025 | COT - HCBU - Building Final | Partial Pass | 9-5-25: per plans, restroom at office area call for it to be ADA. Missing grab bars, flush control must be on accessible side, mirror can be higher than 40" to the reflective surface, toilet paper holder, in wall trash dispenser, remove paint from hammer arrestor located at break room, all interior doors must be at 5 pounds of pressure. | |
| 09/09/2025 | COT - HCBU - Building Final | Passed | 9-9-25: Building final approved. Note: see pending conditions. |