Inspection Status: Partial Pass

Inspection History: COT - HCPL - Plumbing Intermediate 

Permit Number - TC-COM-1024-02030

Inspection Description - COT - HCPL - Plumbing Intermediate 

Inspection Status - Partial Pass

Date Description Inspector Results Comments
03/19/2025 COT - HCPL - Plumbing Intermediate  Partial Pass UG plumbing for Level One, Northwest to D8.
03/21/2025 COT - HCPL - Plumbing Intermediate  Partial Pass Underground plumbing at GL: 3 North, D-E. Ok to cover progress area.
03/28/2025 COT - HCPL - Plumbing Intermediate  Partial Pass 3-28-25, underground plumbing verified on P1N Rev. 4 for level one. Okay to backfill progress areas
04/16/2025 COT - HCPL - Plumbing Intermediate  Partial Pass Grid line A.1-F columns 8-9 all underground plumbing on test okay to back fill progress areas. 4/16/2025
04/17/2025 COT - HCPL - Plumbing Intermediate  Partial Pass Partial pass. X2 10” roof drains underground tie into existing approved. Between Grid lines E and F columns 4 and 5. Okay to backfill. Shading required. 4/17/2025
04/18/2025 COT - HCPL - Plumbing Intermediate  Partial Pass Grid lines B.5-D.5 columns 9-11. underground plumbing on test okay to back fill progress areas. Shading required. 4/18/2025
04/29/2025 COT - HCPL - Plumbing Intermediate  Not Ready
04/30/2025 COT - HCPL - Plumbing Intermediate  Not Ready
05/30/2025 COT - HCPL - Plumbing Intermediate  Partial Pass Domestic water lines 2nd floor. On test. Gauge in room # 2187 Grid A-D column lines 2-7. Okay to proceed progress areas. 5/30/2025
06/03/2025 COT - HCPL - Plumbing Intermediate  Partial Pass Second floor, partial approval, grid lines D through G and 2 through OK to one side several kickers missing require RFI for lack of fire at floor penetrations
06/06/2025 COT - HCPL - Plumbing Intermediate  Partial Pass
06/17/2025 COT - HCPL - Plumbing Intermediate  Not Ready
06/18/2025 COT - HCPL - Plumbing Intermediate  Partial Pass Level Two, A-G, 8-13.
07/02/2025 COT - HCPL - Plumbing Intermediate  Partial Pass 7-2-25: DWV & domestic in wall from gridline's C-G 1-4 verified per plans and under test. Okay to continue with construction at progress areas.
07/17/2025 COT - HCPL - Plumbing Intermediate  Partial Pass
07/25/2025 COT - HCPL - Plumbing Intermediate  Partial Pass Partial pass. In wall. Grid line 6-8 A-G. Okay to proceed progress areas. 7/25/2025
08/08/2025 COT - HCPL - Plumbing Intermediate  Partial Pass
08/12/2025 COT - HCPL - Plumbing Intermediate  Partial Pass