| 01/29/2026 |
COT - HCPL - Plumbing Intermediate |
|
Passed |
|
| 03/19/2025 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
UG plumbing for Level One, Northwest to D8. |
| 03/21/2025 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
Underground plumbing at GL: 3 North, D-E. Ok to cover progress area. |
| 03/28/2025 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
3-28-25, underground plumbing verified on P1N Rev. 4 for level one. Okay to backfill progress areas |
| 04/16/2025 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
Grid line A.1-F columns 8-9 all underground plumbing on test okay to back fill progress areas. 4/16/2025 |
| 04/17/2025 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
Partial pass. X2 10” roof drains underground tie into existing approved. Between Grid lines E and F columns 4 and 5. Okay to backfill. Shading required. 4/17/2025 |
| 04/18/2025 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
Grid lines B.5-D.5 columns 9-11. underground plumbing on test okay to back fill progress areas. Shading required. 4/18/2025 |
| 04/29/2025 |
COT - HCPL - Plumbing Intermediate |
|
Not Ready |
|
| 04/30/2025 |
COT - HCPL - Plumbing Intermediate |
|
Not Ready |
|
| 05/30/2025 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
Domestic water lines 2nd floor. On test. Gauge in room # 2187 Grid A-D column lines 2-7. Okay to proceed progress areas. 5/30/2025 |
| 06/03/2025 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
Second floor, partial approval, grid lines D through G and 2 through OK to one side several kickers missing require RFI for lack of fire at floor penetrations |
| 06/06/2025 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
|
| 06/17/2025 |
COT - HCPL - Plumbing Intermediate |
|
Not Ready |
|
| 06/18/2025 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
Level Two, A-G, 8-13. |
| 07/02/2025 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
7-2-25: DWV & domestic in wall from gridline's C-G 1-4 verified per plans and under test. Okay to continue with construction at progress areas. |
| 07/17/2025 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
|
| 07/25/2025 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
Partial pass. In wall. Grid line 6-8 A-G. Okay to proceed progress areas. 7/25/2025 |
| 08/08/2025 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
|
| 08/12/2025 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
|