Inspection Status: Passed
Inspection History: COT - HCEL - Electrical Above Ceiling
| Date |
Description |
Inspector |
Results |
Comments |
| 01/14/2026 |
COT - HCEL - Electrical Above Ceiling |
|
Passed |
1st floor grids 1-8. Letter has been provided and built as to the typ lamp support detail per the strustructural enengineer. Okay to drop ceiling tiles. 1/14/2026 |
| 06/30/2025 |
COT - HCEL - Electrical Above Ceiling |
|
Partial Pass |
6-30-25: electrical above ceiling on a total of 5 bathroom's located north side of 2nd floor verified per plans. Okay for hard lid at progress areas. |
| 07/09/2025 |
COT - HCEL - Electrical Above Ceiling |
|
Partial Pass |
2302, 2303, 2323, 2005. Hard lid areas approved. Okay to proceed progress areas. 7/9/2025 |
| 07/23/2025 |
COT - HCEL - Electrical Above Ceiling |
|
Partial Pass |
|
| 08/08/2025 |
COT - HCEL - Electrical Above Ceiling |
|
Partial Pass |
|
| 08/14/2025 |
COT - HCEL - Electrical Above Ceiling |
|
Partial Pass |
|
| 08/19/2025 |
COT - HCEL - Electrical Above Ceiling |
|
Partial Pass |
|
| 09/02/2025 |
COT - HCEL - Electrical Above Ceiling |
|
Partial Pass |
|
| 09/25/2025 |
COT - HCEL - Electrical Above Ceiling |
|
Not Ready |
|
| 10/15/2025 |
COT - HCEL - Electrical Above Ceiling |
|
Partial Pass |
|
| 10/27/2025 |
COT - HCEL - Electrical Above Ceiling |
|
Partial Pass |
Electrical, Mechanical, Plumbing above ceiling in store room C17, offices and exam rooms at GL: 7 - 1, store room 2000, vestibule 2000. Ok to place ceiling tile in progress areas. |
| 11/07/2025 |
COT - HCEL - Electrical Above Ceiling |
|
Partial Pass |
|
| 11/13/2025 |
COT - HCEL - Electrical Above Ceiling |
|
Partial Pass |
|
| 12/02/2025 |
COT - HCEL - Electrical Above Ceiling |
|
Partial Pass |
|
| 12/31/2025 |
COT - HCEL - Electrical Above Ceiling |
|
Partial Pass |
Level #1 South portion of structure GL: 8 - 13. Ok to set ceiling tiles in progress areas. |