Inspection Status: Passed

Inspection History: COT - HCEL - Electrical Intermediate

Date Description Inspector Results Comments
01/29/2026 COT - HCEL - Electrical Intermediate Passed
05/30/2025 COT - HCEL - Electrical Intermediate Partial Pass 2nd floor. Grid A-D column lines 2-7. Framing and in wall electrical inspection approved okay to one side progress areas. 5/30/2025
06/03/2025 COT - HCEL - Electrical Intermediate Partial Pass Second floor, partial approval, grid lines D through G and 2 through 7 OK to one side several kickers missing
06/13/2025 COT - HCEL - Electrical Intermediate Partial Pass
06/17/2025 COT - HCEL - Electrical Intermediate Partial Pass
07/08/2025 COT - HCEL - Electrical Intermediate Partial Pass
07/17/2025 COT - HCEL - Electrical Intermediate Not Ready
07/18/2025 COT - HCEL - Electrical Intermediate Partial Pass
08/01/2025 COT - HCEL - Electrical Intermediate Partial Pass
08/08/2025 COT - HCEL - Electrical Intermediate Partial Pass
08/12/2025 COT - HCEL - Electrical Intermediate Partial Pass
08/25/2025 COT - HCEL - Electrical Intermediate Partial Pass
10/31/2025 COT - HCEL - Electrical Intermediate Partial Pass