Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCPL - Plumbing Intermediate
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/26/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | Main sewer line (4”) from structure to man hole. Man hole has been tested by Pima County. | |
| 04/06/2026 | COT - HCPL - Plumbing Intermediate | Not Ready | ||
| 04/08/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | ||
| 04/15/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 4/15/26 Partial for second floor rooms and mechanical rooms three story section only ok to insulate | |
| 04/24/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | ||
| 04/29/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | Level Three, units. | |
| 05/12/2026 | COT - HCPL - Plumbing Intermediate | Not Ready | ||
| 05/13/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | Above ceiling at 1st floor corridor approved. Mechanical shaft approved. 414,415,413,412,411,410,421,420 approved. Okay to proceed progress areas. Pending completions of line sets. 5/13/3026 |
|
| 05/26/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | ||
| 06/03/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | ||
| 06/09/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 6/9/2026 partial pass. 4th floor tubs/showers test approved. | |
| 10/02/2025 | COT - HCPL - Plumbing Intermediate | Not Ready | See plumbing underground. |