Parcel: 11506107B


Addresses:

1910 N STONE AV


Inspection Status: Not Ready

Inspection History: COT - HCBU - Excavation/Rebar/Zoning 

Permit Number - TC-COM-1024-02027

Inspection Description - COT - HCBU - Excavation/Rebar/Zoning 

Inspection Status - Not Ready

Date Description Inspector Results Comments
07/23/2025 COT - HCBU - Excavation/Rebar/Zoning  Not Ready 7.23.25
Discrepancy in plans, not ready
07/25/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 7/25/2025 plans were corrected by the structural engineer. Concrete mat footing at elevator shaft approved. Okay for concrete placement.
08/01/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 7.23.25
Discrepancy in plans, not ready

7/25/2025 plans were corrected by the structural engineer. Concrete mat footing at elevator shaft approved. Okay for concrete placement.
8/1/25: reinforcement per approved plans at elevator shaft walls. ok to proceed with concrete placement
08/11/2025 COT - HCBU - Excavation/Rebar/Zoning  Not Ready
08/14/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Elevator shaft at 32’ - 40’; Ok to place grout in progress areas.
08/20/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Stem wall footings at (South area) from elevator area (SWF2 at -3 ‘ to Northeast corner of structure at WF1 at -5’. Footings at 12 OC with #5 rebar. Ok to set forms and place concrete in progress areas.
09/12/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass
09/22/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Total of 5 steel column footings. Per (SC2) Reinforcements per plan. Okay for concrete placement.
Total of 4 Shear wall footings (3)(SWF2). (1) of (SWF3). Reinforcements per plan. Okay for concrete placement. 9/22/2025
09/29/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Total of 3 Shear wall footing schedule SWF2, SWF3. SWF2 North end of perimeter.
Isolated footing schedule per F4. Closure pour strip #1 East end. Okay for concrete placement. 9/29/2025
10/02/2025 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Stem walls at 16” at North and South sides; East to East side of building; rebar and forms are in place. Ok to place concrete in,progress areas.