Inspection Status: Partial Pass
Inspection History: COT - HCBU - Building Progress
| Date |
Description |
Inspector |
Results |
Comments |
| 03/03/2025 |
COT - HCBU - Building Progress |
|
Partial Pass |
|
| 03/25/2025 |
COT - HCBU - Building Progress |
|
Partial Pass |
Walls of Phase One. |
| 06/04/2025 |
COT - HCBU - Building Progress |
|
Partial Pass |
|
| 06/25/2025 |
COT - HCBU - Building Progress |
|
Partial Pass |
EDS treatment rooms and support areas at Phase I and II. In wall plumbing needs to,be completed. |
| 07/03/2025 |
COT - HCBU - Building Progress |
|
Partial Pass |
Phase II is complete. |
| 08/13/2025 |
COT - HCBU - Building Progress |
|
Not Applicable |
|