Inspection Status: Passed
Inspection History: COT - HCME - Mechanical Above Ceiling
| Date |
Description |
Inspector |
Results |
Comments |
| 01/16/2026 |
COT - HCME - Mechanical Above Ceiling |
|
Passed |
|
| 04/07/2025 |
COT - HCME - Mechanical Above Ceiling |
|
Partial Pass |
above ceiling inspection for the (2) bathrooms on the North side of the Ed Renovation Phase 1. |
| 04/17/2025 |
COT - HCME - Mechanical Above Ceiling |
|
Partial Pass |
Phase I complete. Ok to set ceiling tiles. |
| 07/24/2025 |
COT - HCME - Mechanical Above Ceiling |
|
Partial Pass |
Phase #5, treatment rooms #72, 73, 74, 75, staff rooms 11611, 11612. |
| 07/25/2025 |
COT - HCME - Mechanical Above Ceiling |
|
Partial Pass |
Duct system in place; need registers and vents. |
| 10/09/2025 |
COT - HCME - Mechanical Above Ceiling |
|
Partial Pass |
|