Inspection Status: Not Ready
Inspection History: ENGR Engineering Final
| Date |
Description |
Inspector |
Results |
Comments |
| 10/16/2025 |
ENGR Engineering Final
|
|
Not Ready |
Site is not safe for public access. Construction fencing still surrounding site. Basketball hoops are actively being installed. Beyond those, items missing from the approved plan set include: Rainwater basin is not installed. Only 3 pickleball courts, no lighting; plans call for 6 with lighting. New benches at pickleball courts are missing. New bleachers at basketball courts are missing (included with shade structure scope) |
| 11/05/2025 |
ENGR Engineering Final
|
|
Partial Pass |
Revision required to reflect as-built status. |