Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you can not find what you are looking for please submit a records request.

Inspection Status: Partial Pass

Inspection History: COT - HCBU - Excavation/Rebar/Zoning 

Permit Number - TC-COM-1023-02486

Inspection Description - COT - HCBU - Excavation/Rebar/Zoning 

Inspection Status - Partial Pass

Date Description Inspector Results Comments
06/20/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Building #4. Partial pass. E1, E2, E5, AND E6. GRID LINE 6 FROM NORTH TO SOUTH. TOTAL OF 8. A4, AND A5. B5. C2, C3, C4, C.7(2) C.7(3). D4. D.3(4). WALLS TO ENTRY STAIRWELL. CENTER OF BUILDING A3-A3.3. Okay for concrete placement. 6/20/2024
06/27/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass
07/11/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass by 3rd party inspection
07/18/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass
07/25/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass 7/25/24 partial approval for column footings line E1-E2/B2 AND B2/E1-E.2
09/09/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Building #4. Partial pass. E1, E2, E5, AND E6. GRID LINE 6 FROM NORTH TO SOUTH. TOTAL OF 8. A4, AND A5. B5. C2, C3, C4, C.7(2) C.7(3). D4. D.3(4). WALLS TO ENTRY STAIRWELL. CENTER OF BUILDING A3-A3.3. Okay for concrete placement. 6/20/2024
Student services building by third party ok to place concrete for footers
Building 4 line A/1-4,LINE 4/A-D, D1.8-4, I/A-C.5 AND INTERIOR COLUMN FOOTINGS C&B/ 2,3,4,5
BUILDING 1ELEVATOR PIT FOOTING
7/25/24 partial approval for column footings line E1-E2/B2 AND B2/E1-E.2
Virtual pass for elevator pit, stem wall and column footing OK to place concrete
9/9/24: reinforcement per plan at student service slab on grade.
10/04/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Building #4; West CMU wall (approximately 45’) at 0’ - 4’ AFFE, #5 rebar. OK to place grout in all cells.
12/13/2024 COT - HCBU - Excavation/Rebar/Zoning  Partial Pass Building #4. Partial pass. E1, E2, E5, AND E6. GRID LINE 6 FROM NORTH TO SOUTH. TOTAL OF 8. A4, AND A5. B5. C2, C3, C4, C.7(2) C.7(3). D4. D.3(4). WALLS TO ENTRY STAIRWELL. CENTER OF BUILDING A3-A3.3. Okay for concrete placement. 6/20/2024
Student services building by third party ok to place concrete for footers
Building 4 line A/1-4,LINE 4/A-D, D1.8-4, I/A-C.5 AND INTERIOR COLUMN FOOTINGS C&B/ 2,3,4,5
BUILDING 1ELEVATOR PIT FOOTING
7/25/24 partial approval for column footings line E1-E2/B2 AND B2/E1-E.2
Virtual pass for elevator pit, stem wall and column footing OK to place concrete
9/9/24: reinforcement per plan at student service slab on grade.
12/13/24: reinforcement per plan at student services building level 2 deck GL A-E/1-6.