Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - HCBU - Preslab
Permit Number - TC-COM-1023-02375
Inspection Description - COT - HCBU - Preslab
Inspection Status - Not Ready
Date | Description | Inspector | Results | Comments |
---|---|---|---|---|
02/28/2024 | COT - HCBU - Preslab | Not Ready | ||
03/19/2024 | COT - HCBU - Preslab | Not Ready | ||
04/02/2024 | COT - HCBU - Preslab | Partial Pass | Pre con meeting 4/2/24: (6) pit leveler's reinforcement per plan GL F/2.5 - F/5.5, (4) Dock pit slabs per plan GL F/5.5 - F/7.5, Preslab at office area passed ok to proceed, pending sewer ejector pump, pre slab at remote restrooms ok to proceed. Electrical underground at conference room ok to pour. |
|
04/09/2024 | COT - HCBU - Preslab | Partial Pass | Pre con meeting 4/2/24: (6) pit leveler's reinforcement per plan GL F/2.5 - F/5.5, (4) Dock pit slabs per plan GL F/5.5 - F/7.5, Preslab at office area passed ok to proceed, pending sewer ejector pump, pre slab at remote restrooms ok to proceed. Electrical underground at conference room ok to pour. 4/9/24: smoking shelter concrete slab reinforcement per plan ok to place concrete. |
|
04/11/2024 | COT - HCBU - Preslab | Partial Pass | Pre con meeting 4/2/24: (6) pit leveler's reinforcement per plan GL F/2.5 - F/5.5, (4) Dock pit slabs per plan GL F/5.5 - F/7.5, Preslab at office area passed ok to proceed, pending sewer ejector pump, pre slab at remote restrooms ok to proceed. Electrical underground at conference room ok to pour. 4/9/24: smoking shelter concrete slab reinforcement per plan ok to place concrete. 4/11/24: reinforcement per plan at (4) New Dock pit slab. Ok to pour slab only at new dock pits. Walls at new dock pits missing 2 #4 horizontal. 8 (Mark 46) footings at new canopy south of building per plan ok to place concrete. 8 (Mark 60) footings at new canopy south of building per plan ok to place concrete. Ok to place concrete at entry security electrical underground. |
|
04/17/2024 | COT - HCBU - Preslab | Partial Pass | Pre con meeting 4/2/24: (6) pit leveler's reinforcement per plan GL F/2.5 - F/5.5, (4) Dock pit slabs per plan GL F/5.5 - F/7.5, Preslab at office area passed ok to proceed, pending sewer ejector pump, pre slab at remote restrooms ok to proceed. Electrical underground at conference room ok to pour. 4/9/24: smoking shelter concrete slab reinforcement per plan ok to place concrete. 4/11/24: reinforcement per plan at (4) New Dock pit slab. Ok to pour slab only at new dock pits. Walls at new dock pits missing 2 #4 horizontal. 8 (Mark 46) footings at new canopy south of building per plan ok to place concrete. 8 (Mark 60) footings at new canopy south of building per plan ok to place concrete. Ok to place concrete at entry security electrical underground. 4/17/24: dock pits reinforced per plan ok to pour. |
|
04/19/2024 | COT - HCBU - Preslab | Partial Pass | ||
04/23/2024 | COT - HCBU - Preslab | Not Ready | ||
05/14/2024 | COT - HCBU - Preslab | Partial Pass | Pre con meeting 4/2/24: (6) pit leveler's reinforcement per plan GL F/2.5 - F/5.5, (4) Dock pit slabs per plan GL F/5.5 - F/7.5, Preslab at office area passed ok to proceed, pending sewer ejector pump, pre slab at remote restrooms ok to proceed. Electrical underground at conference room ok to pour. 4/23/24 awaiting third-party inspection for infill on exterior CMU block 4/19/24 pre-slab at pit leveler ok to place concrete w/verticals for block wall 4/9/24: smoking shelter concrete slab reinforcement per plan ok to place concrete. 4/11/24: reinforcement per plan at (4) New Dock pit slab. Ok to pour slab only at new dock pits. Walls at new dock pits missing 2 #4 horizontal. 8 (Mark 46) footings at new canopy south of building per plan ok to place concrete. 8 (Mark 60) footings at new canopy south of building per plan ok to place concrete. Ok to place concrete at entry security electrical underground. 4/17/24: dock pits reinforced per plan ok to pour. 5/14/24: Preslab at sewer ejector passed. Ok to proceed. |
|
07/18/2024 | COT - HCBU - Preslab | Passed | Pre con meeting 4/2/24: (6) pit leveler's reinforcement per plan GL F/2.5 - F/5.5, (4) Dock pit slabs per plan GL F/5.5 - F/7.5, Preslab at office area passed ok to proceed, pending sewer ejector pump, pre slab at remote restrooms ok to proceed. Electrical underground at conference room ok to pour. 4/23/24 awaiting third-party inspection for infill on exterior CMU block 4/19/24 pre-slab at pit leveler ok to place concrete w/verticals for block wall 4/9/24: smoking shelter concrete slab reinforcement per plan ok to place concrete. 4/11/24: reinforcement per plan at (4) New Dock pit slab. Ok to pour slab only at new dock pits. Walls at new dock pits missing 2 #4 horizontal. 8 (Mark 46) footings at new canopy south of building per plan ok to place concrete. 8 (Mark 60) footings at new canopy south of building per plan ok to place concrete. Ok to place concrete at entry security electrical underground. 4/17/24: dock pits reinforced per plan ok to pour. 5/14/24: Preslab at sewer ejector passed. Ok to proceed. 7/18/24: Light pole bases reinforcement per plan for 6 light poles ok to proceed. |