Inspection Status: Not Ready

Inspection History: COT - HCBU - Preslab  

Permit Number - TC-COM-1023-02375

Inspection Description - COT - HCBU - Preslab  

Inspection Status - Not Ready

Date Description Inspector Results Comments
02/28/2024 COT - HCBU - Preslab   Not Ready
03/19/2024 COT - HCBU - Preslab   Not Ready
04/02/2024 COT - HCBU - Preslab   Partial Pass Pre con meeting

4/2/24: (6) pit leveler's reinforcement per plan GL F/2.5 - F/5.5, (4) Dock pit slabs per plan GL F/5.5 - F/7.5, Preslab at office area passed ok to proceed, pending sewer ejector pump, pre slab at remote restrooms ok to proceed. Electrical underground at conference room ok to pour.
04/09/2024 COT - HCBU - Preslab   Partial Pass Pre con meeting

4/2/24: (6) pit leveler's reinforcement per plan GL F/2.5 - F/5.5, (4) Dock pit slabs per plan GL F/5.5 - F/7.5, Preslab at office area passed ok to proceed, pending sewer ejector pump, pre slab at remote restrooms ok to proceed. Electrical underground at conference room ok to pour.
4/9/24: smoking shelter concrete slab reinforcement per plan ok to place concrete.
04/11/2024 COT - HCBU - Preslab   Partial Pass Pre con meeting

4/2/24: (6) pit leveler's reinforcement per plan GL F/2.5 - F/5.5, (4) Dock pit slabs per plan GL F/5.5 - F/7.5, Preslab at office area passed ok to proceed, pending sewer ejector pump, pre slab at remote restrooms ok to proceed. Electrical underground at conference room ok to pour.
4/9/24: smoking shelter concrete slab reinforcement per plan ok to place concrete.
4/11/24: reinforcement per plan at (4) New Dock pit slab. Ok to pour slab only at new dock pits. Walls at new dock pits missing 2 #4 horizontal. 8 (Mark 46) footings at new canopy south of building per plan ok to place concrete. 8 (Mark 60) footings at new canopy south of building per plan ok to place concrete. Ok to place concrete at entry security electrical underground.
04/17/2024 COT - HCBU - Preslab   Partial Pass Pre con meeting

4/2/24: (6) pit leveler's reinforcement per plan GL F/2.5 - F/5.5, (4) Dock pit slabs per plan GL F/5.5 - F/7.5, Preslab at office area passed ok to proceed, pending sewer ejector pump, pre slab at remote restrooms ok to proceed. Electrical underground at conference room ok to pour.
4/9/24: smoking shelter concrete slab reinforcement per plan ok to place concrete.
4/11/24: reinforcement per plan at (4) New Dock pit slab. Ok to pour slab only at new dock pits. Walls at new dock pits missing 2 #4 horizontal. 8 (Mark 46) footings at new canopy south of building per plan ok to place concrete. 8 (Mark 60) footings at new canopy south of building per plan ok to place concrete. Ok to place concrete at entry security electrical underground.
4/17/24: dock pits reinforced per plan ok to pour.
04/19/2024 COT - HCBU - Preslab   Partial Pass
04/23/2024 COT - HCBU - Preslab   Not Ready
05/14/2024 COT - HCBU - Preslab   Partial Pass Pre con meeting

4/2/24: (6) pit leveler's reinforcement per plan GL F/2.5 - F/5.5, (4) Dock pit slabs per plan GL F/5.5 - F/7.5, Preslab at office area passed ok to proceed, pending sewer ejector pump, pre slab at remote restrooms ok to proceed. Electrical underground at conference room ok to pour.
4/23/24 awaiting third-party inspection for infill on exterior CMU block
4/19/24 pre-slab at pit leveler ok to place concrete w/verticals for block wall
4/9/24: smoking shelter concrete slab reinforcement per plan ok to place concrete.
4/11/24: reinforcement per plan at (4) New Dock pit slab. Ok to pour slab only at new dock pits. Walls at new dock pits missing 2 #4 horizontal. 8 (Mark 46) footings at new canopy south of building per plan ok to place concrete. 8 (Mark 60) footings at new canopy south of building per plan ok to place concrete. Ok to place concrete at entry security electrical underground.
4/17/24: dock pits reinforced per plan ok to pour.
5/14/24: Preslab at sewer ejector passed. Ok to proceed.
07/18/2024 COT - HCBU - Preslab   Passed Pre con meeting

4/2/24: (6) pit leveler's reinforcement per plan GL F/2.5 - F/5.5, (4) Dock pit slabs per plan GL F/5.5 - F/7.5, Preslab at office area passed ok to proceed, pending sewer ejector pump, pre slab at remote restrooms ok to proceed. Electrical underground at conference room ok to pour.
4/23/24 awaiting third-party inspection for infill on exterior CMU block
4/19/24 pre-slab at pit leveler ok to place concrete w/verticals for block wall
4/9/24: smoking shelter concrete slab reinforcement per plan ok to place concrete.
4/11/24: reinforcement per plan at (4) New Dock pit slab. Ok to pour slab only at new dock pits. Walls at new dock pits missing 2 #4 horizontal. 8 (Mark 46) footings at new canopy south of building per plan ok to place concrete. 8 (Mark 60) footings at new canopy south of building per plan ok to place concrete. Ok to place concrete at entry security electrical underground.
4/17/24: dock pits reinforced per plan ok to pour.
5/14/24: Preslab at sewer ejector passed. Ok to proceed.
7/18/24: Light pole bases reinforcement per plan for 6 light poles ok to proceed.