Inspection Status: Partial Pass
Inspection History: COT - LCBU - Framing
| Date |
Description |
Inspector |
Results |
Comments |
| 02/25/2026 |
COT - LCBU - Framing |
|
Partial Pass |
2/25/26: Mechanical framing opening approved ok to proceed. |
| 03/11/2026 |
COT - LCBU - Framing |
|
Partial Pass |
3-11-26: interior metal framing at the 3 high walls verified per plans. Horizontal Bracing at 8' o.c. & with proper shot pin placement. Okay to continue with construction at progress areas. |
| 03/24/2026 |
COT - LCBU - Framing |
|
Partial Pass |
3-24-26: interior wall framing along the north side of building (warehouse side) approved. Okay to insulate & install drywall at progress areas. (pending wall framing at doors). |
| 03/25/2026 |
COT - LCBU - Framing |
|
Partial Pass |
3-25-26: partial pass pending engineer letter regarding bracing @4'. |