Permit: TC-COM-0925-01709

Parcel: 14026040C


Addresses:

2850 E DREXEL RD

Inspection Status: Partial Pass

Inspection History: COT - LCBU - Framing

Date Description Inspector Results Comments
02/25/2026 COT - LCBU - Framing Partial Pass 2/25/26: Mechanical framing opening approved ok to proceed.
03/11/2026 COT - LCBU - Framing Partial Pass 3-11-26: interior metal framing at the 3 high walls verified per plans. Horizontal Bracing at 8' o.c. & with proper shot pin placement. Okay to continue with construction at progress areas.
03/24/2026 COT - LCBU - Framing Partial Pass 3-24-26: interior wall framing along the north side of building (warehouse side) approved. Okay to insulate & install drywall at progress areas. (pending wall framing at doors).
03/25/2026 COT - LCBU - Framing Partial Pass 3-25-26: partial pass pending engineer letter regarding bracing @4'.
05/05/2026 COT - LCBU - Framing Partial Pass 5-5-26: pending engineer letter regarding bracing @4'. Please submit engineer/architect's letter regarding listed above item to the city for review. There is nothing showing in system for this
05/20/2026 COT - LCBU - Framing Partial Pass 5-20-26: pending RFI review & approval. See previous notes.
05/21/2026 COT - LCBU - Framing Partial Pass 5-21-26: this inspection will be cleared out if & when revision letter is approved by the city.
06/17/2026 COT - LCBU - Framing Re-inspection required 6-17-26: add a gfci breaker for switch at break room, install metallic labeling at rooftop disconnects and identify circuit/purpose, provide power to tv & kitchen receptacles, pending framing RFI approval from city and outstanding conditions.
06/22/2026 COT - LCBU - Framing Partial Pass 6-22-26: pending city approval on framing RFI.
06/25/2026 COT - LCBU - Framing Passed 6-25-26: RFI for framing has been submitted to the city-Framing approved.