Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Not Ready
Inspection History: COT - LCBU - Excavation/Rebar/Zoning
| Date |
Description |
Inspector |
Results |
Comments |
| 09/11/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Not Ready |
Curbs poured. Call in inspection for charger pads after forming and reinforcing installation and prior to pour. |
| 09/15/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
Okay to pour charger pads |
| 09/18/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
Excessive cross slope at radius, and at bottom landing. all changes in direction must be less than 2% in any direction. Ensure that all ramps remain less than 8.3% |
| 09/23/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Canceled |
Rebar did not arrive. |
| 10/01/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
10.2.26: 5 caisson approved for canopy |