Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - LCEL - Electrical Progress
Permit Number - TC-COM-0924-01879
Inspection Description - COT - LCEL - Electrical Progress
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/08/2025 | COT - LCEL - Electrical Progress | Partial Pass | Total of 8 light pole bases. West end of field. Per detail J on page approved. Reinforcements, depth per plan. UFER and conduit in place. Okay for concrete placement. East end of field total of 4 light pole bases per detail L. Reinforcements, depth per plan. UFER and conduit in place. Okay for concrete placement. 5/8/2025 |
|
| 07/25/2025 | COT - LCEL - Electrical Progress | Partial Pass | 4” conduit from main power,in,street to transformer on site (approximately 200 feet). Ok to cover progress area. | |
| 09/12/2025 | COT - LCEL - Electrical Progress | Passed |