Inspection History Details
Inspection Status: Not Ready
Inspection History: ENGR Engineering Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/29/2025 | ENGR Engineering Final | Not Ready | 05-29-25, Not ready for final inspections due to Banner requesting that, materials, temporary staging, temporary fencing, dumpster and port-a-Jon be left on site until the stucco company has completed their phase of the work. All ADA pathways have met the compliance of the ADA at this time. | |
| 07/03/2025 | ENGR Engineering Final | Passed | 7/03/25 All Material and fencing related to this permit is gone. Port a Jon will be gone at end of day. There is 40 linear ft of temporary fencing and material that is the responsibility of Banner subcontractor CRS/ATI. Kitchell Contracting is not part of this work. Scope of work for Permit is complete. This is unrelated warranty work on stucco to be completed by end of July. ADA access is unimpeded, and area is safe. |