Inspection History Details
Inspection Status: Re-inspection required
Inspection History: COT - LCBU - Building Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 10/07/2024 | COT - LCBU - Building Final | Re-inspection required | 10/7/24: ADA Requirements at bathroom must be met, bathroom signage required, unsatisfied conditions need to be addressed prior to final inspection, letter head required at means of egress stating doors must remain unlocked while building is occupied. Copper piping at water heater requires coated hangers or 10mill tape at hangers to avoid copper making contact with dissimilar metals. | |
| 11/07/2024 | COT - LCBU - Building Final | Re-inspection required | 11/7/2024. Not ready. Floor sink not tied into the sewer system. When flushing the toilet it shuts off all the water to sinks and other fixtures. Need to insulate plumbing lines. Still missing signage per previous notes. | |
| 11/27/2024 | COT - LCBU - Building Final | Re-inspection required | unsatisfied conditions need to be addressed prior to final inspection, letter head required at means of egress stating doors must remain unlocked while building is occupied. Copper piping at water heater requires coated hangers or 10mill tape at hangers to avoid copper making contact with dissimilar metals. 11/7/2024. Not ready. Floor sink not tied into the sewer system. When flushing the toilet it shuts off all the water to sinks and other fixtures. Need to insulate plumbing lines. Still missing signage per previous notes. 11/27/24: plumbing lines required to be insulated and signage required per previous notes. |
|
| 12/03/2024 | COT - LCBU - Building Final | Passed |