Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Building Progress
Permit Number - TC-COM-0923-02246
Inspection Description - COT - HCBU - Building Progress
Inspection Status - Partial Pass
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/21/2025 | COT - HCBU - Building Progress | Partial Pass | 8-21-25: reinforcement/details at conveyor trench at Gridline B 1-5 verified per plan. Okay for concrete placement at progress areas. | |
| 09/29/2025 | COT - HCBU - Building Progress | Partial Pass | 9-29-25: reinforcement for cmu wall verified per plans. Okay to grout 1st lift on west interior wall at 4' & 2nd lift for west exterior wall at 8'. | |
| 10/24/2025 | COT - HCBU - Building Progress | Partial Pass | 10/24/25 Vacuum arches caisson ok to pour, please submit details. currently not on the plan set. 10/24/25 Vacuum arches plumbing and electrical conduit. |
|
| 10/28/2025 | COT - HCBU - Building Progress | Canceled | ||
| 11/25/2025 | COT - HCBU - Building Progress | Partial Pass | 11/25/2025 bathroom nailing pattern approved. |