Inspection Status: Partial Pass
Inspection History: COT - LCPL - Plumbing Final
| Date |
Description |
Inspector |
Results |
Comments |
| 06/03/2026 |
COT - LCPL - Plumbing Final |
|
Partial Pass |
6-3-26: reinforcement/lintel at back door & dowels with epoxy at ADA restroom approved. 3rd party inspector verified epoxy at both areas. Please submit report to the city for review & approval. Okay to pour back slab on grade at restroom and okay to grout cmu cells at back door. |
| 08/18/2026 |
COT - LCPL - Plumbing Final |
|
Re-inspection required |
8-18-26: lower grab bars at ADA restroom to 36 aff, lower restroom mirror to 40" to the reflective surface, flush control must be on accessible side, missing vertical grab bar, install ADA restroom signs adjacent to door-60" maximum, add insulation to hot copper line at water heater, a water sterilization report is required- submit report to the city for review/approval. |
| 08/21/2026 |
COT - LCPL - Plumbing Final |
|
Passed |
8-21-26: plumbing final approved. Contractor provided me with a copy of the water sterilization report and has submitted a copy to the city for review/approval. |