Inspection Status: Not Ready
Inspection History: COT - LCEL - Electrical Final
| Date |
Description |
Inspector |
Results |
Comments |
| 03/04/2026 |
COT - LCEL - Electrical Final |
|
Not Ready |
3-4-26: not ready for electrical final. |
| 07/14/2026 |
COT - LCEL - Electrical Final |
|
Re-inspection required |
7-14-26: could not test all receptacles due to freshly installed tile, missing panel schedule add GFCI receptacles at restrooms, install water heater & electrical tie in. Reschedule when ready. |
| 07/20/2026 |
COT - LCEL - Electrical Final |
|
Re-inspection required |
7-20-26: missing knockouts at panel, missing panel schedules, add covers to all light receptacles, missing smoke and heat detectors-see plans for details, back restroom receptacle must be gfci, provide ladder for roof access, install all equipment.Stopped inspection-additional items may be noted. |
| 08/06/2026 |
COT - LCEL - Electrical Final |
|
Not Ready |
Missing panel schedule. Provide 3’ clearance at sub panel. cannot very second sub panel. Provide gfci receptacle at laundry area. Provide a shackle lock at water heater breaker. Secure seal tight at water heater. Gfci breaker shall be dedicated in bathrooms. Roof still needs to be inspected. 8/6/2026 |
| 08/13/2026 |
COT - LCEL - Electrical Final |
|
Passed |
|