Permit: TC-COM-0825-01553

Parcel: 12006316B


Addresses:

4225 S 6TH AV

Inspection Status: Not Ready

Inspection History: COT - LCPL - Plumbing Intermediate 

Date Description Inspector Results Comments
03/12/2026 COT - LCPL - Plumbing Intermediate  Not Ready 3-12-26: not ready for intermediates.
04/03/2026 COT - LCPL - Plumbing Intermediate  Re-inspection required 4-3-26: add shot pins within 6" at the ends of each plate and 32" o.c. thereafter. Add stud-shoes to the studs located at the southeast corner-non load bearing cannot be over notched more than 40%. Have architect of record submit a new floor plan showing the relocation of the ADA restrooms. Okay to continue with construction and will check for corrections at the intermediates.
04/10/2026 COT - LCPL - Plumbing Intermediate  Re-inspection required 4-10-26: add Boca plates to DWV at sole & top plates, stud shoes are required at the southeast corner-see previous notes, fire foam all penetrations at top plates, a revision is required for the the new ADA bathroom showing the relocation of DWV together with a detail regarding reinforcement/ epoxy information (epoxy will require a 3rd party inspection) for pour back. The DWV at the ADA restroom needs to be wrapped prior to pour back.
Note: an electric water heater's pressure relief valve (TPR valve) can drain into a mop sink, provided it maintains an indirect connection with an air gap to prevent backflow into the heater.
04/29/2026 COT - LCPL - Plumbing Intermediate  Re-inspection required 4-29-26: firefoam all penetrations at top plates throughout and missing a fire alarm in hallway near back restroom.Pending RFI for restroom underground plumbing with pour back details. Epoxy for dowels will require a 3rd party inspection.
05/13/2026 COT - LCPL - Plumbing Intermediate  Partial Pass 5-13-26: plumbing intermediates approved. Okay to drywall progress areas but schedule a drywall screw inspection prior to tape & texture.
05/20/2026 COT - LCPL - Plumbing Intermediate  Passed 5-20-26: drywall screw inspection approved. Okay to tape & texture.