| 10/23/2025 |
COT - LCPL - Plumbing Intermediate |
|
Not Ready |
|
| 10/28/2025 |
COT - LCPL - Plumbing Intermediate |
|
Re-inspection required |
10-28-25: an 18" transition from pex to copper is required at water heater, at lavatories and at copper to pex stemming out of bathroom south wall. In wall DWV must be under test, Add straps to copper line in bathroom. |
| 10/29/2025 |
COT - LCPL - Plumbing Intermediate |
|
Passed |
|