Inspection Status: Partial Pass
Inspection History: COT - LCBU - Excavation/Rebar/Zoning
| Date |
Description |
Inspector |
Results |
Comments |
| 01/30/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
1-30-26: reinforcement/excavation for slab on grade at equipment pad verified per plans (dowels/epoxy also verified by 3rd party). Reinforcement for 2 columns verified per S2.0 detail C1/F1-102 and the other per detail 107. Okay for concrete placement at progress areas. |
| 02/03/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
New machine room 130. Reinforcement per plan okay for concrete placement. 2/3/2026 |
| 02/04/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
2-4-26: pre slab/excavation & reinforcement for slab on grade and columns/columns tie on footings along the east side of building verified per plans/ S2.0, S2.0/details 101, 105, 108, 109, C3/F2, C3/F3. Okay for concrete placement at progress areas. |
| 02/09/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
East side: footings and slab areas for equipment pad and fabrication area. Ok to place concrete in,-regress areas. |
| 02/18/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Partial Pass |
2-18-26: excavation/reinforcement at slab on grade/footing located on west side verified per RFI26. RFI to be submitted to the city for review. Also verified reinforcement for pad on west side per detail 109-#4 @12" o.c.... Okay to pour pad and RFI26 at own risk pending city approval. |
| 02/25/2026 |
COT - LCBU - Excavation/Rebar/Zoning |
|
Passed |
|