Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO.
If you cannot find what you are looking for please
submit a records request.
Inspection Status: Partial Pass
Inspection History: COT - LCBU - Building Final
| Date |
Description |
Inspector |
Results |
Comments |
| 06/11/2026 |
COT - LCBU - Building Final |
|
Partial Pass |
6-11-26: missing downspouts, warehouse doors located on northwest side not installed , and no power to receptacle at room 125, pending approval for new SES revision together with outstanding conditions. |
| 07/14/2026 |
COT - LCBU - Building Final |
|
Partial Pass |
7-14-26: pending installation of warehouse doors and DP inspections. |
| 07/21/2026 |
COT - LCBU - Building Final |
|
Partial Pass |
7-21-26: partial pass pending pre-fab warehouse doors. Okay to apply for a Level 2 TCO and occupy office spaces only. A barrier from warehouse and office space areas is required to prevent entry to warehouse. |
| 08/04/2026 |
COT - LCBU - Building Final |
|
Passed |
|