Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - LCEL - Electrical Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 08/06/2024 | COT - LCEL - Electrical Final | Partial Pass | 8/6/24: electrical underground from CT Cabinet to new utility transformer per plans ok to backfill progress area. | |
| 10/16/2024 | COT - LCEL - Electrical Final | Partial Pass | 8/6/24: electrical underground from CT Cabinet to new utility transformer per plans ok to backfill progress area. 10/16/24: meter clearance Ev-chargers are wired appropriately and panel schedule has been labeled. |
|
| 11/13/2024 | COT - LCEL - Electrical Final | Passed |