Inspection Status: Passed
Inspection History: COT - HCPL - Plumbing Intermediate
| Date |
Description |
Inspector |
Results |
Comments |
| 03/06/2024 |
COT - HCPL - Plumbing Intermediate |
|
Passed |
Plumbing rough-in is complete for 2 hand sinks on hallway walls. Okay to proceed with installation of insulation and drywall. |
| 04/12/2024 |
COT - HCPL - Plumbing Intermediate |
|
Not Ready |
|
| 05/01/2024 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
|
| 05/07/2024 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
|
| 05/17/2024 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
5/17/24: soiled work room, and hand sink nourishment 13660D |
| 05/28/2024 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
Med gas for OR10. OR4. OR11. (Operating rooms) all under pressure. Okay to proceed progress areas. Air handling unit 3 and 4. Mechanical piping. Post cool piping under pressure. 5/28/2024 |
| 07/03/2024 |
COT - HCPL - Plumbing Intermediate |
|
Not Ready |
|
| 07/10/2024 |
COT - HCPL - Plumbing Intermediate |
|
Canceled |
7/10/24: canceled per contractor |
| 08/30/2024 |
COT - HCPL - Plumbing Intermediate |
|
Partial Pass |
Ok to install border ceiling tiles |
| 11/07/2024 |
COT - HCPL - Plumbing Intermediate |
|
Passed |
|