Microfiche records prior to 2006 have not been completely digitized and may not be available yet on PRO. If you cannot find what you are looking for please submit a records request.

PRO is currently experiencing an outage. Some documents and records may not be available on PRO momentarily. We apologize for the inconvenience and are working to restore full access.

Inspection Status: Partial Pass

Inspection History: COT - LCEL - Electrical Intermediate

Date Description Inspector Results Comments
02/19/2026 COT - LCEL - Electrical Intermediate Partial Pass Partial pass for electric underground an light pole , ok to backfill
02/24/2026 COT - LCEL - Electrical Intermediate Partial Pass 2-24-26: verified conduits stub ups/ per schedule at pads & at mini power zone.
03/05/2026 COT - LCEL - Electrical Intermediate Partial Pass 3-5-26: all electrical construction verified per approved plans. Switchgear, dispensers & power cabinets all torqued to specifications.Anchor bolt installation on cabinets verified by 3rd party- report to be submitted to the city for review. Pending completion of MPZ-1 and primary wires. Okay to continue with construction at progress areas.
06/26/2026 COT - LCEL - Electrical Intermediate Passed 6-26-26: electrical intermediate approved.