Inspection Status: Partial Pass
Inspection History: COT - LCEL - Electrical Intermediate
| Date |
Description |
Inspector |
Results |
Comments |
| 02/19/2026 |
COT - LCEL - Electrical Intermediate |
|
Partial Pass |
Partial pass for electric underground an light pole , ok to backfill |
| 02/24/2026 |
COT - LCEL - Electrical Intermediate |
|
Partial Pass |
2-24-26: verified conduits stub ups/ per schedule at pads & at mini power zone. |
| 03/05/2026 |
COT - LCEL - Electrical Intermediate |
|
Partial Pass |
3-5-26: all electrical construction verified per approved plans. Switchgear, dispensers & power cabinets all torqued to specifications.Anchor bolt installation on cabinets verified by 3rd party- report to be submitted to the city for review. Pending completion of MPZ-1 and primary wires. Okay to continue with construction at progress areas. |
| 06/26/2026 |
COT - LCEL - Electrical Intermediate |
|
Passed |
6-26-26: electrical intermediate approved. |