Inspection Status: Partial Pass
Inspection History: COT - LCBU - Framing
| Date |
Description |
Inspector |
Results |
Comments |
| 09/12/2025 |
COT - LCBU - Framing |
|
Partial Pass |
9/12/25: A small fur-out wall has been constructed over the plumbing in the Boy's restroom. Approved |
| 11/13/2025 |
COT - LCBU - Framing |
|
Partial Pass |
11-13-25: partial pass on East demising wall. Contractor in the process of fire taping penetrations-okay to continue TI at progress areas. Schedule inspection when all fire taping is complete together with a drywall nailing inspection prior to tape & texture |
| 11/24/2025 |
COT - LCBU - Framing |
|
Partial Pass |
11-24-25: demising wall at south side office approved. Okay to install drywall but schedule a drywall nailing inspection prior to tape & texture. |
| 12/19/2025 |
COT - LCBU - Framing |
|
Passed |
12-19-25: approved. |