Inspection Status: Passed
Inspection History: COT - CSOL - Electrical Underground Solar Project
| Date |
Description |
Inspector |
Results |
Comments |
| 02/19/2026 |
COT - CSOL - Electrical Underground Solar Project |
|
Passed |
|
| 09/25/2025 |
COT - CSOL - Electrical Underground Solar Project |
|
Partial Pass |
Building E to D |
| 09/30/2025 |
COT - CSOL - Electrical Underground Solar Project |
|
Partial Pass |
Partial pass. 60' section of trench that starts from building D and runs to building F. The trench includes 2, 2" pipes for AC wires from PV combiner panels. It also has 2, 1" pipes that will have low voltage data wires. Okay to backfill progress areas. Shading required. 9/30/2025 |
| 10/03/2025 |
COT - CSOL - Electrical Underground Solar Project |
|
Partial Pass |
D to F around Laundry Room |
| 10/08/2025 |
COT - CSOL - Electrical Underground Solar Project |
|
Partial Pass |
From gym and Building C to Laundry room. |