Inspection History Details
Inspection Status: Not Ready
Inspection History: ENGR Engineering Final
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 09/08/2026 | ENGR Engineering Final | Not Ready | -Porta-potty and Rolloff Dumpster are still on site and should be removed prior to Final. -East exterior storefront wall/entryway is not complete. -Water Sterilization and Air Balancing conditions on permit need to be satisfied prior to Final. -Reschedule this inspection when ready. |
|
| 09/10/2026 | ENGR Engineering Final | Partial Pass | Dumpster and Porta potty are scheduled for pick up. Conditions are satisfied. - One section of store front door and windows are not complete but, this is an additional entryway. Other entryways are functional. Restrict access to this area for safety until finished. OK to apply for level 2 TCO. |
|
| 09/18/2026 | ENGR Engineering Final | Passed |