Inspection History Details
Inspection Status: Passed
Inspection History: COT - LCPL - Plumbing Intermediate
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/06/2026 | COT - LCPL - Plumbing Intermediate | Passed | 2-6-26: approved. | |
| 02/06/2026 | COT - LCPL - Plumbing Intermediate | Passed | 2-6-26: plumbing intermediate approved. | |
| 10/01/2025 | COT - LCPL - Plumbing Intermediate | Re-inspection required | 10-1-25: new DWV for hand sink must be under test, submit a revision for changes on water heater; intended change regarding the thermostatic mixing valve underneath lavatory, & information/calcs for actual size of grease interceptor-Existing interceptor does not match plans | |
| 10/10/2025 | COT - LCPL - Plumbing Intermediate | Re-inspection required | 10-10-25: Grease interceptor & DWV at cashier area must be under test. Test domestic at 100 psi, add strapping to DWV located just east of freezer and add plastic bushings to copper lines making contact with metal framing at cashier & bar areas. | |
| 10/14/2025 | COT - LCPL - Plumbing Intermediate | Partial Pass | 10-14-25: in wall domestic, DWV, & grease interceptor verified under test. Plastic bushings for in wall domestic at metal framing in place. Provide a plastic bushings around DWV making contact with metal framing at order/cashier location-Provide a picture prior to closing wall. Verified that all penetrations separating the suite at the east wall have been properly sealed. Okay to continue with TI at progress areas. Note: verified gas line test at 15 psi, however, all gas appliances require shut off valves prior to clearance being issued SWG. |