Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Interior Shear Bracing
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 02/11/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | Level #3, inter shear walls,in Sections B and Section C. | |
| 02/23/2026 | COT - HCBU - Interior Shear Bracing | Canceled | Will reschedule for 24 February. | |
| 03/10/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 3/10/26: exterior shear walls approved per plans specifications @ levels 5 and 6 GL C-G/3-4. Ok to proceed | |
| 03/26/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 3/26/26: 4TH FLOOR SHEAR WALLS APPROVED (pending plumbing walls), Densgalss approved at exterior walls at GL E/6-11 (floors 2-4),Densgalss approved at exterior walls second layer at GL F-G/4 (floors 3-6) | |
| 04/01/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 4/1/26: 5th floor interior shear bracing (partial pass) pending plumbing walls. 2nd layer Densgalss approved at GL E/1-3 & GL B.5-E.5/1 floors 3- | |
| 04/17/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 4/16/16: 613,615,655,654,652,653,650,651,648,646,644,643,642,641 (interior shear walls , pending plumbing walls) | |
| 04/27/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 4/27/26: 7th floor shear, 790,760,759,758,756,757,713 |
|
| 04/29/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 4/29/26: interior shear walls approved at 7th floor units (715,755,754,752,753,750,751,748), first layer drywall in electrical rooms east wall only (276,376,476,576,676,767) | |
| 05/01/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 5/1/26:Interior Shear Inspection for Level 7 Area A | |
| 05/07/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 5/7/2026 Nail Inspection for Level 2 West Side Units 1st Layer Drywall. rooms 212-240 approved. | |
| 05/22/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 5/21/26:nail inspection Electrical room 1st layer rooms (372,472,572,672,772) | |
| 06/23/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | Partial pass. Interior Shear Wall Inspection for Plumbing Walls Units 443,416,413,460,465. 6/23/2026 | |
| 06/24/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | Partial pass. Drywall nailing approved in units 254,255,252,253,250,251,257,213,215. 6/24/2026 | |
| 07/17/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 7/17/2026 Partial pass. 5th floor Osb shear wall at east wall unit 560, stair shaft Osb shear unit 562. 6th floor Osb shear wall stair shaft (plumbing walls) 662, 660. |
|
| 07/23/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 7/23/26: Plumbing walls shear walls have been completed on floors 5-7 room #513,516,613,616,713,716. | |
| 07/29/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 7/29/26" PLUMBING WALL SHEARWALLS HAVE BEEN COMPLETED 743,643,543 | |
| 08/07/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 4th floor drywall screw inspection units 415,416,422,417. RC channel in place 4th floor corridors. |
|
| 08/10/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 8/10/2026 7th floor RC channel in place at ceiling. Partial pass courtesy inspection. Unit 762 4th floor drywall screw inspection approved at units 430,436, |
|
| 08/13/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 8/13/2026 Partial pass. 7th floor RC channel in place. Units 762,759. | |
| 08/17/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 8/17/2026 Partial pass. Drywall screw inspection 4th floor units 419. 1st floor units 110,108,104,102. | |
| 08/19/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 8/19/2026 Partial pass. RC channel in place. 7th floor units 760,758,754. Drywall in place unit 443. | |
| 08/20/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 8/20/2026 Partial pass. Drywall screw inspection 7th floor unit 759. RC channel in place Unit 756 approved. |
|
| 08/21/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 8/21/2026 Partial pass. Drywall screw inspection 7th floor units 762,760, Partial pass. RC channel in place 7th floor unit 757,715,713. |
|
| 08/24/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | ||
| 08/25/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 8/25/2026 Partial pass. 7th floor rc channel in place. Units 748,750,751,755. Drywall in place. Units 757,756. 3rd floor unit 346 approved. |
|
| 08/26/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 8/26/2026 Partial pass. 7th floor RC channel in place unit 746. Drywall unit 715,342. Okay to proceed progress areas. |
|
| 08/27/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 8/27/2026 Partial pass. Drywall screw inspection approved 7th floor units 716,713,752,748. RC channel in place. 7th floor unit 743. 3rd floor corridors RC channel in place. Pending north section for wall installation. |
|
| 08/28/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 8/28/2026 3rd floor north corridor RC channel complete at walls. 7th floor drywall screw inspection unit 750. |
|
| 09/01/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 9/1/26: INTERIOR SHEAR WALL ROOM 753 AND RC CHANNEL ROOM 656,654,658,660 | |
| 09/02/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 9/2/26: RC CHANNEL ROOM 741 | |
| 09/03/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | ||
| 09/04/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | 9/4/26: RC Channel approved in units 655,657,659 | |
| 09/08/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass | ||
| 09/09/2026 | COT - HCBU - Interior Shear Bracing | Partial Pass |