Inspection Status: Partial Pass
Inspection History: COT - HCBU - Interior Shear Bracing
| Date |
Description |
Inspector |
Results |
Comments |
| 02/11/2026 |
COT - HCBU - Interior Shear Bracing |
|
Partial Pass |
Level #3, inter shear walls,in Sections B and Section C. |
| 02/23/2026 |
COT - HCBU - Interior Shear Bracing |
|
Canceled |
Will reschedule for 24 February. |
| 03/10/2026 |
COT - HCBU - Interior Shear Bracing |
|
Partial Pass |
3/10/26: exterior shear walls approved per plans specifications @ levels 5 and 6 GL C-G/3-4. Ok to proceed |
| 03/26/2026 |
COT - HCBU - Interior Shear Bracing |
|
Partial Pass |
3/26/26: 4TH FLOOR SHEAR WALLS APPROVED (pending plumbing walls), Densgalss approved at exterior walls at GL E/6-11 (floors 2-4),Densgalss approved at exterior walls second layer at GL F-G/4 (floors 3-6) |
| 04/01/2026 |
COT - HCBU - Interior Shear Bracing |
|
Partial Pass |
4/1/26: 5th floor interior shear bracing (partial pass) pending plumbing walls. 2nd layer Densgalss approved at GL E/1-3 & GL B.5-E.5/1 floors 3- |