Inspection History Details
Inspection Status: Requested
Inspection History: COT - HCPL - Plumbing Above Ceiling
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| COT - HCPL - Plumbing Above Ceiling | Requested | |||
| 05/01/2026 | COT - HCPL - Plumbing Above Ceiling | Re-inspection required | 5.1.26: Hot water lines 3/4" and larger shall be properly insulated with minimum R3 insulation, properly support pex line and DWV throughout, dryer exhaust must be constructed of smooth material, kitchen hood shall be constructed of smooth materials, fire caulking required throughout at common walls, proper secure low voltage, back to back receptacles with inserts are required to have putty pad installed, provide Documentation on how large penetrations will be sealed, separate MC cable from copper lines, seal all penetrations (from low volt, mechanical, sprinkler, plumbing) | |
| 05/05/2026 | COT - HCPL - Plumbing Above Ceiling | Partial Pass | 5/5/26: M.E.P APPROVED ABOVE CEILING IN STUDIO UNITS 1ST FLOOR (112,114,116,118,120,122,124,126,128,130,132,134,136,138,140) | |
| 05/06/2026 | COT - HCPL - Plumbing Above Ceiling | Partial Pass | 5/6/2026 MEP approved above ceilings 2nd floor units 212-240. Okay to proceed progress areas. | |
| 05/08/2026 | COT - HCPL - Plumbing Above Ceiling | Partial Pass | 5/8/2026 MEP approved above ceilings 2nd floor units 262,259,260,258,256,254,255,252,253,250,251,257,213,215. Okay to proceed progress areas. | |
| 05/13/2026 | COT - HCPL - Plumbing Above Ceiling | Partial Pass | 5/13/26:In-Wall and Above Inspection for Unit 112 | |
| 05/15/2026 | COT - HCPL - Plumbing Above Ceiling | Partial Pass | 4th floor DWV, pex along with CPVC in rooms 413,414,415,457,455,454,452,453 on test. Inter & Above ceiling 3rd floor rooms 362,359,360,358,356,354,352,353,350,351,348,346 approved. Okay to proceed progress areas. 5/15/2026 |