Permit: TC-COM-0624-01172

Parcel: 11504505A


Addresses:

812 E SPEEDWAY BL

Inspection Status: Re-inspection required

Inspection History: COT - HCPL - Plumbing Above Ceiling

Date Description Inspector Results Comments
05/01/2026 COT - HCPL - Plumbing Above Ceiling Re-inspection required 5.1.26: Hot water lines 3/4" and larger shall be properly insulated with minimum R3 insulation, properly support pex line and DWV throughout, dryer exhaust must be constructed of smooth material, kitchen hood shall be constructed of smooth materials, fire caulking required throughout at common walls, proper secure low voltage, back to back receptacles with inserts are required to have putty pad installed, provide Documentation on how large penetrations will be sealed, separate MC cable from copper lines, seal all penetrations (from low volt, mechanical, sprinkler, plumbing)
05/05/2026 COT - HCPL - Plumbing Above Ceiling Partial Pass 5/5/26: M.E.P APPROVED ABOVE CEILING IN STUDIO UNITS 1ST FLOOR (112,114,116,118,120,122,124,126,128,130,132,134,136,138,140)
05/06/2026 COT - HCPL - Plumbing Above Ceiling Partial Pass 5/6/2026 MEP approved above ceilings 2nd floor units 212-240. Okay to proceed progress areas.
05/08/2026 COT - HCPL - Plumbing Above Ceiling Partial Pass 5/8/2026 MEP approved above ceilings 2nd floor units 262,259,260,258,256,254,255,252,253,250,251,257,213,215. Okay to proceed progress areas.
05/13/2026 COT - HCPL - Plumbing Above Ceiling Partial Pass 5/13/26:In-Wall and Above Inspection for Unit 112
05/15/2026 COT - HCPL - Plumbing Above Ceiling Partial Pass 4th floor DWV, pex along with CPVC in rooms 413,414,415,457,455,454,452,453 on test.
Inter & Above ceiling 3rd floor rooms 362,359,360,358,356,354,352,353,350,351,348,346 approved. Okay to proceed progress areas. 5/15/2026
05/18/2026 COT - HCPL - Plumbing Above Ceiling Partial Pass 5/18/26: shower wall fire taping rooms (134,136,138), shower walls 2nd floor screw inspection ( 212,214,216,218,220,222,224,226,228,230), MEP rooms 316,322,317,330,319, over notched studs require fix, code compliance nail plates required at plumbing walls
05/20/2026 COT - HCPL - Plumbing Above Ceiling Partial Pass 5/20/26: 3rd floor MEP in wall and above ceiling units 316,322,317,330,319,336,341,342,343,315,313,355,357) ok to proceed with progress areas.
05/29/2026 COT - HCPL - Plumbing Above Ceiling Partial Pass 5/29/26:MEP approved In rooms 462,460,459,471,458,456,454, 452,450,453,455,457,413
06/01/2026 COT - HCPL - Plumbing Above Ceiling Partial Pass Partial pass 4th floor units 415,484,416,422,417,430,419,436,485,441,442 approved. Okay to proceed progress areas. 6/1/2026
06/03/2026 COT - HCPL - Plumbing Above Ceiling Partial Pass 6/3/26: above ceiling MEP and framing approved In rooms (184,179.4,179.3,179.2,180,180.183,183A,178.1,178.2,178.3,178.4,178.5,178.6,)
06/04/2026 COT - HCPL - Plumbing Above Ceiling Partial Pass 6/4/26: MEP approval in rooms 446,448,451,443

Fastener spacing approval at 2nd layer behind tubs in rooms 251,250,252,253,255,257,260,259,213,215,

Fire tape at areas behind tubs in rooms 254,256,258,262
06/08/2026 COT - HCPL - Plumbing Above Ceiling Partial Pass 6/8/26: 3rd floor corridor approved and draft stop between partition walls.
06/12/2026 COT - HCPL - Plumbing Above Ceiling Partial Pass 6/12/26: CORRIDOR 2ND FLOOR ABOVE CEILING MEP, IN WALL 2ND FLOOR (279,280.1,280.2,280.3,280.4,280.5,280.6), 5th floor (pvc,CPVC,pex rooms 557,513,555,516,515 pressure test approved), 6th floor pvc test (657,613,656,616,615), 7th floor pvc (756,713,756,716,715)
06/18/2026 COT - HCPL - Plumbing Above Ceiling Partial Pass 6/18/26: MEP APPROVED IN ROOMS 562,559,560,558(pending mechanical), 556

ATS ROD ROOMS 416-413-415-457-455
06/24/2026 COT - HCPL - Plumbing Above Ceiling Partial Pass Level 4 all corridors approved. Okay to proceed progress areas. 6/24/2026
06/25/2026 COT - HCPL - Plumbing Above Ceiling Partial Pass Partial pass. MEP approved 5th floor units 516,513,515,557,555. 6/25/2026
06/26/2026 COT - HCPL - Plumbing Above Ceiling Partial Pass Partial pass. MEP approved 5th floor units 554,552,553,550,551,548,546,543,542,541. 6/26/2026
06/29/2026 COT - HCPL - Plumbing Above Ceiling Partial Pass 6/29/26: 5TH floor MEP Corridor and above ceiling and in wall.
Interior shear-bracing 2nd floor corridor and shaft#
07/02/2026 COT - HCPL - Plumbing Above Ceiling Partial Pass 7/2/2026 Partial pass. Lighting in place at Exterior garage soffit north east corner. MEP approved units 662,659,660,658,656,654,657,655,615,613. Okay to proceed progress areas.
COT - HCPL - Plumbing Above Ceiling Scheduled