Permit: TC-COM-0624-01172

Parcel: 11504505A


Addresses:

812 E SPEEDWAY BL

Inspection Status: Requested

Inspection History: COT - HCPL - Plumbing Intermediate 

Date Description Inspector Results Comments
COT - HCPL - Plumbing Intermediate  Requested
01/13/2026 COT - HCPL - Plumbing Intermediate  Partial Pass Level #1 and P-1; waste lines at 2 1/2” - 6” lines under hydro test.
02/18/2026 COT - HCPL - Plumbing Intermediate  Partial Pass Level #1; room units and main entry lobby/amenities rooms
03/17/2026 COT - HCPL - Plumbing Intermediate  Partial Pass 3/17/26: AREA C DWV,PVC,CPVC in rooms (256,257,258,259,260,262) pressure test approved
03/19/2026 COT - HCPL - Plumbing Intermediate  Partial Pass 3/18/26: Area C (213,215)
Area B 255,254,252,253, 212,214,216,218,220,222,224,226,282, 281.1
3/19/26: Area A (228,230,232,234,236,238,240,280.2,280.4,280.1,280.3,280.5,280.6,281,279,278,278.4278.5, 2nd floor elevator lobby,251,250,
04/08/2026 COT - HCPL - Plumbing Intermediate  Partial Pass 4/8/26: DWV under test in rooms 362,359,360,358,356
04/09/2026 COT - HCPL - Plumbing Intermediate  Partial Pass 4/9/26: 3rd floor Area C pex 362,359,360,358,356, pressure test only
04/16/2026 COT - HCPL - Plumbing Intermediate  Partial Pass 4/15/26:
DWV and Domestic:313,315,357,355,354,352(pex pending),353
04/20/2026 COT - HCPL - Plumbing Intermediate  Partial Pass 4/20/26: Inspection for Plumbing Straps for Level 2213,257,259,260,258,256,254,255,252,253,250,251,279,280.1,280.3,238,236,234,232,230,228,226,224,283,222,220218,216,214,21215,
04/27/2026 COT - HCPL - Plumbing Intermediate  Partial Pass 4/27/26:Plumbing 316 DWV and pex pressure 322,317,330(PVC),319(pvc),341 (restroom pvc) 441 (restoroom pvc),419,430,417,422, 416,415 restroom only (pvc)
05/01/2026 COT - HCPL - Plumbing Intermediate  Re-inspection required 5.1.26: Hot water lines 3/4" and larger shall be properly insulated with minimum R3 insulation, properly support pex line and DWV throughout, dryer exhaust must be constructed of smooth material, kitchen hood shall be constructed of smooth materials, fire caulking required throughout at common walls, proper secure low voltage, back to back receptacles with inserts are required to have putty pad installed, provide Documentation on how large penetrations will be sealed, separate MC cable from copper lines, seal all penetrations (from low volt, mechanical, sprinkler, plumbing)
05/04/2026 COT - HCPL - Plumbing Intermediate  Not Ready
05/06/2026 COT - HCPL - Plumbing Intermediate  Canceled 5/6/2026 canceled per contractor.
05/07/2026 COT - HCPL - Plumbing Intermediate  Partial Pass 5/7/2026 Partial pass. DWV and pex under test in all units below. 341,342,343,344,346,348,351,350
441,442,443,444,446,448,451,450.
Pending CPVC not under test.
Pending 444,344 pex lines.
05/15/2026 COT - HCPL - Plumbing Intermediate  Partial Pass 4th floor DWV, pex along with CPVC in rooms 413,414,415,457,455,454,452,453 on test.
Inter & Above ceiling 3rd floor rooms 362,359,360,358,356,354,352,353,350,351,348,346 approved. Okay to proceed progress areas. 5/15/2026
08/15/2025 COT - HCPL - Plumbing Intermediate  Partial Pass Waste line at 6” at GL: 2.5/B.5 - E.5. Under hydro test, Ok to cover progress areas at Level P-1.
08/19/2025 COT - HCPL - Plumbing Intermediate  Partial Pass Basement level; 4” waste line at D.5/10.5 - 5.5. OK to cover progress areas.
09/08/2025 COT - HCPL - Plumbing Intermediate  Partial Pass This inspection is for plumbing underground at GL: 4 - 8/E.9 - F.9. Waste and vent lines at 2” - 6”. Ok to cover progress areas
09/11/2025 COT - HCPL - Plumbing Intermediate  Partial Pass Plumbing underground at GL: F.5/9 - 11.5 (3” - 6” waste and vent lines) Ok to cover progress areas.
09/17/2025 COT - HCPL - Plumbing Intermediate  Partial Pass Plumbing underground for waste and vents lines (2 1/2” - 6”) at GL: F/7.1 - 12. OK to cover progress areas.
09/26/2025 COT - HCPL - Plumbing Intermediate  Partial Pass Plumbing underground: 6” and 4” waste lines at GL: 13/E.5 - A. OK to cover progress areas.
10/01/2025 COT - HCPL - Plumbing Intermediate  Partial Pass Plumbing underground for 2” - 4” waste lines at GL: G/7 - 8, 8/G - F. OK to cover progress areas.
10/02/2025 COT - HCPL - Plumbing Intermediate  Partial Pass Waste and vent lines at GL: E.9/9 - 10, E.9 - G/9 - 10, (Plumbing underground). Ok to cover progress areas.
11/20/2025 COT - HCPL - Plumbing Intermediate  Partial Pass Waste and vent lines(2 1/2” - 6”) parking garage lower level. All lines are under hydro test.