Inspection History: COT - HCPL - Plumbing Intermediate
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/13/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | Level #1 and P-1; waste lines at 2 1/2” - 6” lines under hydro test. | |
| 02/18/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | Level #1; room units and main entry lobby/amenities rooms | |
| 03/17/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 3/17/26: AREA C DWV,PVC,CPVC in rooms (256,257,258,259,260,262) pressure test approved | |
| 03/19/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 3/18/26: Area C (213,215) Area B 255,254,252,253, 212,214,216,218,220,222,224,226,282, 281.1 3/19/26: Area A (228,230,232,234,236,238,240,280.2,280.4,280.1,280.3,280.5,280.6,281,279,278,278.4278.5, 2nd floor elevator lobby,251,250, |
|
| 04/08/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 4/8/26: DWV under test in rooms 362,359,360,358,356 | |
| 04/09/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 4/9/26: 3rd floor Area C pex 362,359,360,358,356, pressure test only | |
| 04/16/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 4/15/26: DWV and Domestic:313,315,357,355,354,352(pex pending),353 |
|
| 04/20/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 4/20/26: Inspection for Plumbing Straps for Level 2213,257,259,260,258,256,254,255,252,253,250,251,279,280.1,280.3,238,236,234,232,230,228,226,224,283,222,220218,216,214,21215, | |
| 04/27/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 4/27/26:Plumbing 316 DWV and pex pressure 322,317,330(PVC),319(pvc),341 (restroom pvc) 441 (restoroom pvc),419,430,417,422, 416,415 restroom only (pvc) | |
| 05/01/2026 | COT - HCPL - Plumbing Intermediate | Re-inspection required | 5.1.26: Hot water lines 3/4" and larger shall be properly insulated with minimum R3 insulation, properly support pex line and DWV throughout, dryer exhaust must be constructed of smooth material, kitchen hood shall be constructed of smooth materials, fire caulking required throughout at common walls, proper secure low voltage, back to back receptacles with inserts are required to have putty pad installed, provide Documentation on how large penetrations will be sealed, separate MC cable from copper lines, seal all penetrations (from low volt, mechanical, sprinkler, plumbing) | |
| 05/04/2026 | COT - HCPL - Plumbing Intermediate | Not Ready | ||
| 05/06/2026 | COT - HCPL - Plumbing Intermediate | Canceled | 5/6/2026 canceled per contractor. | |
| 05/07/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 5/7/2026 Partial pass. DWV and pex under test in all units below. 341,342,343,344,346,348,351,350 441,442,443,444,446,448,451,450. Pending CPVC not under test. Pending 444,344 pex lines. |
|
| 05/15/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 4th floor DWV, pex along with CPVC in rooms 413,414,415,457,455,454,452,453 on test. Inter & Above ceiling 3rd floor rooms 362,359,360,358,356,354,352,353,350,351,348,346 approved. Okay to proceed progress areas. 5/15/2026 |
|
| 05/18/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 5/18/26: shower wall fire taping rooms (134,136,138), shower walls 2nd floor screw inspection ( 212,214,216,218,220,222,224,226,228,230), MEP rooms 316,322,317,330,319, over notched studs require fix, code compliance nail plates required at plumbing walls | |
| 05/22/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 5/22/26: DWV and Domestic pressure test in rooms (458,460,459,462) | |
| 05/29/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 5/29/26:MEP approved In rooms 462,460,459,471,458,456,454, 452,450,453,455,457,413 | |
| 06/01/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | Partial pass 4th floor units 415,484,416,422,417,430,419,436,485,441,442 approved. Okay to proceed progress areas. 6/1/2026 | |
| 06/03/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 6.3.26: PVC+CPVC+PEX pressure test approved in rooms 559,560,558,556,562. PVC PRESSURE TEST APPROVED IN ROOMS 759,760,758,756,762 AND 659,660,658,656,662 | |
| 06/08/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 6/8/26: 3rd floor corridor approved and draft stop between partition walls. | |
| 06/12/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 6/12/26: CORRIDOR 2ND FLOOR ABOVE CEILING MEP, IN WALL 2ND FLOOR (279,280.1,280.2,280.3,280.4,280.5,280.6), 5th floor (pvc,CPVC,pex rooms 557,513,555,516,515 pressure test approved), 6th floor pvc test (657,613,656,616,615), 7th floor pvc (756,713,756,716,715) | |
| 06/16/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 6/16/26: 5th floor (PVC,CPVC,PEX) rooms #550-552-553-551-554-548 pressure test approved, 6th floor (PVC) rooms# 654,652,650,653,651,648 pressure test approved | |
| 06/18/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 6/18/26: MEP APPROVED IN ROOMS 562,559,560,558(pending mechanical), 556 ATS ROD ROOMS 416-413-415-457-455 |
|
| 06/23/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | Partial pass. CPVC, PVC, & PEX under test 5th floor units 546, 544,543,542,541. 6th floor PVC under test units 646,644,643,641,642. 7th floor PVC under test units 746,744,743,741,742. 6/23/2026 |
|
| 06/24/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | Level 4 all corridors approved. Okay to proceed progress areas. 6/24/2026 | |
| 06/25/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | Partial pass. MEP approved 5th floor units 516,513,515,557,555. 6/25/2026 | |
| 06/26/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | Partial pass. MEP approved 5th floor units 554,552,553,550,551,548,546,543,542,541. 6/26/2026 | |
| 06/29/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 6/29/26: 5TH floor MEP Corridor and above ceiling and in wall. Interior shear-bracing 2nd floor corridor and shaft# |
|
| 06/30/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | Partial pass. Section C. Tubs under test. Units 462,459,460,458,456, 457. Pex/PVC under test units 616,613,615,662,659,660,658,657,655,654,652,653,650,651,648,646,643,641,642. 6/30/2026 |
|
| 07/02/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 7/2/2026 Partial pass. Lighting in place at Exterior garage soffit north east corner. MEP approved units 662,659,660,658,656,654,657,655,615,613. Okay to proceed progress areas. | |
| COT - HCPL - Plumbing Intermediate | Scheduled | |||
| 08/15/2025 | COT - HCPL - Plumbing Intermediate | Partial Pass | Waste line at 6” at GL: 2.5/B.5 - E.5. Under hydro test, Ok to cover progress areas at Level P-1. | |
| 08/19/2025 | COT - HCPL - Plumbing Intermediate | Partial Pass | Basement level; 4” waste line at D.5/10.5 - 5.5. OK to cover progress areas. | |
| 09/08/2025 | COT - HCPL - Plumbing Intermediate | Partial Pass | This inspection is for plumbing underground at GL: 4 - 8/E.9 - F.9. Waste and vent lines at 2” - 6”. Ok to cover progress areas | |
| 09/11/2025 | COT - HCPL - Plumbing Intermediate | Partial Pass | Plumbing underground at GL: F.5/9 - 11.5 (3” - 6” waste and vent lines) Ok to cover progress areas. | |
| 09/17/2025 | COT - HCPL - Plumbing Intermediate | Partial Pass | Plumbing underground for waste and vents lines (2 1/2” - 6”) at GL: F/7.1 - 12. OK to cover progress areas. | |
| 09/26/2025 | COT - HCPL - Plumbing Intermediate | Partial Pass | Plumbing underground: 6” and 4” waste lines at GL: 13/E.5 - A. OK to cover progress areas. | |
| 10/01/2025 | COT - HCPL - Plumbing Intermediate | Partial Pass | Plumbing underground for 2” - 4” waste lines at GL: G/7 - 8, 8/G - F. OK to cover progress areas. | |
| 10/02/2025 | COT - HCPL - Plumbing Intermediate | Partial Pass | Waste and vent lines at GL: E.9/9 - 10, E.9 - G/9 - 10, (Plumbing underground). Ok to cover progress areas. | |
| 11/20/2025 | COT - HCPL - Plumbing Intermediate | Partial Pass | Waste and vent lines(2 1/2” - 6”) parking garage lower level. All lines are under hydro test. |