Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCPL - Plumbing Roof Drains
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/25/2026 | COT - HCPL - Plumbing Roof Drains | Partial Pass | Partial pass. Total of 26 roof drains under test. Okay to release pressure. Pending securing roof drains two points. 6/25/2026 | |
| 06/26/2026 | COT - HCPL - Plumbing Roof Drains | Partial Pass | Partial pass. MEP approved 5th floor units 554,552,553,550,551,548,546,543,542,541. 6/26/2026 | |
| 06/29/2026 | COT - HCPL - Plumbing Roof Drains | Partial Pass | 6/29/26: 5TH floor MEP Corridor and above ceiling and in wall. Interior shear-bracing 2nd floor corridor and shaft# |
|
| 07/02/2026 | COT - HCPL - Plumbing Roof Drains | Passed | ||
| 12/16/2025 | COT - HCPL - Plumbing Roof Drains | Partial Pass | Roof drain at Southeast corner of structure; 3” drain line and vent lines. Ok to,cover progress areas. |