Inspection History Details
Inspection Status: Partial Pass
Inspection History: COT - HCBU - Framing
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 01/05/2026 | COT - HCBU - Framing | Partial Pass | Metal stud framing on Level #2, Section C. | |
| 01/07/2026 | COT - HCBU - Framing | Partial Pass | Level #3; Section C decking. Sheathing and straps are in place. Ok to erect walls in progress areas. | |
| 01/16/2026 | COT - HCBU - Framing | Partial Pass | 4th Floor Decking of West side of structure. Ok to frame in progress areas. | |
| 01/22/2026 | COT - HCBU - Framing | Partial Pass | Level #4 deck; Section A. Ok to frame walls in progress areas. | |
| 01/26/2026 | COT - HCBU - Framing | Partial Pass | Metal interior framing at Level #2; sections A & B. | |
| 01/28/2026 | COT - HCBU - Framing | Partial Pass | Level #4, Northeast portion of deck; straps are in place. Ok to frame walls in progress area. | |
| 01/30/2026 | COT - HCBU - Framing | Partial Pass | Level #5, section C deck. Straps are in place; Ok to construct walls in progress area. | |
| 02/04/2026 | COT - HCBU - Framing | Partial Pass | Level #5, Section C deck; strapping in place, nail pattern is correct. Ok to lay-out and erect walls. | |
| 02/06/2026 | COT - HCBU - Framing | Partial Pass | Exterior wall framing of West side of structure at levels #1 and #2. Ok to cover progress areas with sheathing. | |
| 02/09/2026 | COT - HCBU - Framing | Partial Pass | Level #1; Interior West side room units: metal framing. | |
| 02/10/2026 | COT - HCBU - Framing | Partial Pass | Level #2 West side room units interior metal framing. | |
| 02/11/2026 | COT - HCBU - Framing | Partial Pass | Level #5; Sections A, B, and C decking. Required straps and sheathing are in place. Ok to lay-out and erect interior walls. | |
| 02/12/2026 | COT - HCBU - Framing | Partial Pass | Level #2, East side room units; metal stud framing. Main lobby area and amenities rooms; metal stud framing. | |
| 02/17/2026 | COT - HCBU - Framing | Canceled | Canceled due to inclement weather. Will reschedule 18 February | |
| 02/24/2026 | COT - HCBU - Framing | Partial Pass | Level #3 shear walls and hold downs (SW #1, 2, 3, 6). Level #6 decking for Section B; straps in place. Ok to lay-out and construct walls. | |
| 02/27/2026 | COT - HCBU - Framing | Partial Pass | Level #6 decking; Ok to lay-out and erect walls and install straps. | |
| 03/04/2026 | COT - HCBU - Framing | Partial Pass | Level #7; decking. Straps in place in Section B. Ok to lay-out and erect walls. | |
| 03/10/2026 | COT - HCBU - Framing | Partial Pass | 3/10/26: Deck nailing L7 Section approved. Ok to proceed. | |
| 03/16/2026 | COT - HCBU - Framing | Partial Pass | 3/16/26: Nail Deck Inspection for Level 7 Floor Area B | |
| 03/17/2026 | COT - HCBU - Framing | Partial Pass | 3/16/26: Nail Deck Inspection for Level 7 Floor Area B and Area A | |
| 04/02/2026 | COT - HCBU - Framing | Partial Pass | 4/2/26: Exterior Framing for Lobby Area | |
| 04/21/2026 | COT - HCBU - Framing | Partial Pass | 4/21/26: 1st layer gypsum board at shafts #5,6,7 approved from 3rd floor to 6th floor. Ok to proceed with 2nd layer | |
| 04/29/2026 | COT - HCBU - Framing | Partial Pass | 4/29/26: interior shear walls approved at 7th floor units (715,755,754,752,753,750,751,748), first layer drywall in electrical rooms east wall only (276,376,476,576,676,767) | |
| 05/01/2026 | COT - HCBU - Framing | Partial Pass | 5/1/26:Level 1 Units Nail Inspection for 1st Layer Drywall studios west room (fasteners must be 3/8" from edge and shall not penetrate more than 1/8") | |
| 05/05/2026 | COT - HCBU - Framing | Partial Pass | 5/5/26: Drywall inspection for electrical rooms east wall (in rooms 276,376,476,576,676,776) | |
| 05/11/2026 | COT - HCBU - Framing | Partial Pass | 5/11/26: DRYWALL NAILING FOR SHAFT #8 at 3rd and 4th floor approved for first layer. | |
| 05/12/2026 | COT - HCBU - Framing | Partial Pass | 5/12/26: DRYWALL NAILING FOR SHAFT #8 at 3rd and 4th floor approved for second layer. | |
| 05/14/2026 | COT - HCBU - Framing | Partial Pass | 5/14/2027 Nail Inspection for Shafts and Level 1 Unit Restrooms. 134,130,126,122,118 fire tape approved behind and to the side of shower walls. | |
| 05/15/2026 | COT - HCBU - Framing | Partial Pass | Inter & Above ceiling 3rd floor rooms 362,359,360,358,356,354,352,353,350,351,348,346 approved. Okay to proceed progress areas. 5/15/2026 | |
| 05/18/2026 | COT - HCBU - Framing | Partial Pass | 5/18/26: shower wall fire taping rooms (134,136,138), shower walls 2nd floor screw inspection ( 212,214,216,218,220,222,224,226,228,230), MEP rooms 316,322,317,330,319, over notched studs require fix, code compliance nail plates required at plumbing walls | |
| 05/19/2026 | COT - HCBU - Framing | Partial Pass | 5/19/26: drywall screw nailing behind shower walls 2nd floor fire tape approved at units 212-230, screw inspection approved in units 232-240. (Pending 218) | |
| 05/27/2026 | COT - HCBU - Framing | Partial Pass | 5/27/26: Level 2 - 1st Layer Drywall for demising walls and corridor walls. | |
| 05/29/2026 | COT - HCBU - Framing | Partial Pass | 5/29/26:MEP approved In rooms 462,460,459,471,458,456,454, 452,450,453,455,457,413 | |
| 06/01/2026 | COT - HCBU - Framing | Partial Pass | Partial pass 4th floor units 415,484,416,422,417,430,419,436,485,441,442 approved. Okay to proceed progress areas. 6/1/2026 | |
| 06/03/2026 | COT - HCBU - Framing | Partial Pass | 6/3/26: above ceiling MEP and framing approved In rooms (184,179.4,179.3,179.2,180,180.183,183A,178.1,178.2,178.3,178.4,178.5,178.6,) | |
| 06/05/2026 | COT - HCBU - Framing | Partial Pass | 6/5/26: Drywall nailing approved at (112,114,116,118,120,122,124,126,128,130,132,136,138,188,187,186),electrical room 7th floor rooms 772,672,572,472,372, 773,573,373 | |
| 06/08/2026 | COT - HCBU - Framing | Partial Pass | 6/8/26: 3rd floor corridor approved and draft stop between partition walls. | |
| 06/09/2026 | COT - HCBU - Framing | Partial Pass | 6/9/26: Shaft # 8 3rd-4th floor (fire tape), shaft (#4,5,6,7,8,9) 3rd-6th floor (fire tape), rooms (372,472,572,672,772,373,573,773) fire tape, elec room (376,476,576,676,776) 2nd layer, shaft # 4 and 5 floors 3-6 | |
| 06/10/2026 | COT - HCBU - Framing | Partial Pass | 6/10/26: drywall nailing approved at rooms (212,214,216,218,220,222,224,226,228,230,232,234,236,238,240), fire tape behind tubs in rooms (251,250,253,255,262,260,257,213) | |
| 06/11/2026 | COT - HCBU - Framing | Partial Pass | 6/11/26: fire tape at shaft #2 and 3 on 7th floor approved, 2nd layer drywall screw inspection at shaft. #4 at 7th floor, 4th floor draft stop approved. | |
| 06/12/2026 | COT - HCBU - Framing | Partial Pass | 6/12/26: CORRIDOR 2ND FLOOR ABOVE CEILING MEP, IN WALL 2ND FLOOR (279,280.1,280.2,280.3,280.4,280.5,280.6), 5th floor (pvc,CPVC,pex rooms 557,513,555,516,515 pressure test approved), 6th floor pvc test (657,613,656,616,615), 7th floor pvc (756,713,756,716,715) | |
| 06/16/2026 | COT - HCBU - Framing | Partial Pass | 6/16/26: SHAFT #3 and #4 screw pattern approved @2nd layer (6th floor), Shaft #1 screw pattern @2nd layer (7th floor). | |
| 06/17/2026 | COT - HCBU - Framing | Partial Pass | 6/17/26: DRYWALL INSPECTION APPROVED IN ROOMS 262-259-260-258-256, SHAFT#2 6th floor approved 2nd layer | |
| 06/18/2026 | COT - HCBU - Framing | Partial Pass | 6/18/26: MEP APPROVED IN ROOMS 562,559,560,558(pending mechanical), 556 ATS ROD ROOMS 416-413-415-457-455 |
|
| 06/22/2026 | COT - HCBU - Framing | Partial Pass | Partial pass. Inspection for the Hold-down System( ATS RODS) on Levels 4 & 5 approved. 6/22/2026 | |
| 06/24/2026 | COT - HCBU - Framing | Partial Pass | Level 4 all corridors approved. Okay to proceed progress areas. 6/24/2026 | |
| 06/25/2026 | COT - HCBU - Framing | Partial Pass | Partial pass. MEP approved 5th floor units 516,513,515,557,555. 6/25/2026 | |
| 06/26/2026 | COT - HCBU - Framing | Partial Pass | Partial pass. MEP approved 5th floor units 554,552,553,550,551,548,546,543,542,541. 6/26/2026 | |
| 06/29/2026 | COT - HCBU - Framing | Partial Pass | 6/29/26: 5TH floor MEP Corridor and above ceiling and in wall. Interior shear-bracing 2nd floor corridor and shaft# |
|
| 07/02/2026 | COT - HCBU - Framing | Partial Pass | 7/2/2026 Partial pass. Lighting in place at Exterior garage soffit north east corner. MEP approved units 662,659,660,658,656,654,657,655,615,613. Okay to proceed progress areas. | |
| 07/06/2026 | COT - HCBU - Framing | Partial Pass | 7/6/2026 Partial pass. Level 6 Framing and MEP In-Wall & Above Ceiling. Units 652,653,650,651,648,646,643,642,641 | |
| 07/09/2026 | COT - HCBU - Framing | Partial Pass | 7/9/2026 Partial pass. Level 6 Corridor Framing and MEP Above Ceiling & In-Wall along with unit 644. | |
| 07/13/2026 | COT - HCBU - Framing | Partial Pass | 7/13/2027 Partial pass. Level 3 Unit drywall nail inspection units 359,360,358,356,354,352,353,350,351,348. Pending rfi on ceilings due to the type of fasteners and lengths. | |
| 07/15/2026 | COT - HCBU - Framing | Partial Pass | 7/15/2026 Partial pass. 7th floor units 762,759,760,758 approved. | |
| 07/16/2026 | COT - HCBU - Framing | Partial Pass | 7/16/26: partial pass. 178,178.1,178.2,178.3,178.4,178.5,178.6,180,180.1,179,179.2,179.3,179.4 | |
| 07/20/2026 | COT - HCBU - Framing | Partial Pass | 7/20/26: partial pass 7th floor units 756,257,713,716,715 approved. | |
| 07/23/2026 | COT - HCBU - Framing | Partial Pass | 7/23/26: Plumbing walls shear walls have been completed on floors 5-7 room #513,516,613,616,713,716. | |
| 07/28/2026 | COT - HCBU - Framing | Partial Pass | 7/28/26: Drywall nailing 355,357,313,315 (interior walls only),316 (pending shaft),322,317,330,319,336,456,458,460,459,462,280.1,280.3 Fire tape 762,759,760,758,756,754,752,755,757,715,713,716 |
|
| 07/30/2026 | COT - HCBU - Framing | Partial Pass | 7/30/26: 7TH FLOOR UNIT 741 MEP approved. Electrical in wall at 7th floor corridor pending supports throughout at nm cable at boxes, above ceiling pending lighting, mechanical approved, plumbing above ceiling approved, plumbing wall requires FHA where top plates are notched greater than 50%. 1st floor above ceiling in lobby are approved, 1st floor room 183 in wall and above ceiling approved. | |
| 07/31/2026 | COT - HCBU - Framing | Partial Pass | 7/31/2026 partial pass. 1st floor units MEP and above ceilings 102,104,106,108,113. 2nd floor unit MEP and above ceiling 278 pending point 1-2-3. |
|
| 08/03/2026 | COT - HCBU - Framing | Partial Pass | 8/3/2026 Partial pass. Level 4 Drywall Nail Inspection Area B & A East Side. Units 446,448,451,450,453,452,454,458 approved. | |
| 08/05/2026 | COT - HCBU - Framing | Partial Pass | 8/5/2026 Partial pass. Drywall screw inspection 4th floor unit 413,457,455 approved. | |
| 08/07/2026 | COT - HCBU - Framing | Partial Pass | 4th floor drywall screw inspection units 415,416,422,417. RC channel in place 4th floor corridors. |
|
| 08/10/2026 | COT - HCBU - Framing | Partial Pass | 8/10/2026 7th floor RC channel in place at ceiling. Partial pass courtesy inspection. Unit 762 4th floor drywall screw inspection approved at units 430,436, |
|
| 08/12/2026 | COT - HCBU - Framing | Partial Pass | 8/12/26: drywall nailing inspection approved lobby,183,183.A | |
| 08/13/2026 | COT - HCBU - Framing | Partial Pass | 8/13/2026 Partial pass. 7th floor RC channel in place. Units 762,759. | |
| 08/17/2026 | COT - HCBU - Framing | Canceled | 8/17/2026 RC inspection canceled per contractor. | |
| 08/19/2026 | COT - HCBU - Framing | Partial Pass | 8/19/2026 Partial pass. RC channel in place. 7th floor units 760,758,754. Drywall in place unit 443. | |
| 08/20/2026 | COT - HCBU - Framing | Partial Pass | 8/20/2026 Partial pass. Drywall screw inspection 7th floor unit 759. RC channel in place Unit 756 approved. |
|
| COT - HCBU - Framing | Scheduled | |||
| 12/29/2025 | COT - HCBU - Framing | Partial Pass | Lecel #3, Section C decking . Ensure all straps are in place and sheathing edges are properly secured. |