Permit: TC-COM-0624-01172

Parcel: 11504505A


Addresses:

812 E SPEEDWAY BL

Inspection Status: Partial Pass

Inspection History: COT - HCBU - Framing

Date Description Inspector Results Comments
01/05/2026 COT - HCBU - Framing Partial Pass Metal stud framing on Level #2, Section C.
01/07/2026 COT - HCBU - Framing Partial Pass Level #3; Section C decking. Sheathing and straps are in place. Ok to erect walls in progress areas.
01/16/2026 COT - HCBU - Framing Partial Pass 4th Floor Decking of West side of structure. Ok to frame in progress areas.
01/22/2026 COT - HCBU - Framing Partial Pass Level #4 deck; Section A. Ok to frame walls in progress areas.
01/26/2026 COT - HCBU - Framing Partial Pass Metal interior framing at Level #2; sections A & B.
01/28/2026 COT - HCBU - Framing Partial Pass Level #4, Northeast portion of deck; straps are in place. Ok to frame walls in progress area.
01/30/2026 COT - HCBU - Framing Partial Pass Level #5, section C deck. Straps are in place; Ok to construct walls in progress area.
02/04/2026 COT - HCBU - Framing Partial Pass Level #5, Section C deck; strapping in place, nail pattern is correct. Ok to lay-out and erect walls.
02/06/2026 COT - HCBU - Framing Partial Pass Exterior wall framing of West side of structure at levels #1 and #2. Ok to cover progress areas with sheathing.
02/09/2026 COT - HCBU - Framing Partial Pass Level #1; Interior West side room units: metal framing.
02/10/2026 COT - HCBU - Framing Partial Pass Level #2 West side room units interior metal framing.
02/11/2026 COT - HCBU - Framing Partial Pass Level #5; Sections A, B, and C decking. Required straps and sheathing are in place. Ok to lay-out and erect interior walls.
02/12/2026 COT - HCBU - Framing Partial Pass Level #2, East side room units; metal stud framing. Main lobby area and amenities rooms; metal stud framing.
02/17/2026 COT - HCBU - Framing Canceled Canceled due to inclement weather. Will reschedule 18 February
02/24/2026 COT - HCBU - Framing Partial Pass Level #3 shear walls and hold downs (SW #1, 2, 3, 6). Level #6 decking for Section B; straps in place. Ok to lay-out and construct walls.
02/27/2026 COT - HCBU - Framing Partial Pass Level #6 decking; Ok to lay-out and erect walls and install straps.
03/04/2026 COT - HCBU - Framing Partial Pass Level #7; decking. Straps in place in Section B. Ok to lay-out and erect walls.
03/10/2026 COT - HCBU - Framing Partial Pass 3/10/26: Deck nailing L7 Section approved. Ok to proceed.
03/16/2026 COT - HCBU - Framing Partial Pass 3/16/26: Nail Deck Inspection for Level 7 Floor Area B
03/17/2026 COT - HCBU - Framing Partial Pass 3/16/26: Nail Deck Inspection for Level 7 Floor Area B and Area A
04/02/2026 COT - HCBU - Framing Partial Pass 4/2/26: Exterior Framing for Lobby Area
04/21/2026 COT - HCBU - Framing Partial Pass 4/21/26: 1st layer gypsum board at shafts #5,6,7 approved from 3rd floor to 6th floor. Ok to proceed with 2nd layer
04/29/2026 COT - HCBU - Framing Partial Pass 4/29/26: interior shear walls approved at 7th floor units (715,755,754,752,753,750,751,748), first layer drywall in electrical rooms east wall only (276,376,476,576,676,767)
05/01/2026 COT - HCBU - Framing Partial Pass 5/1/26:Level 1 Units Nail Inspection for 1st Layer Drywall studios west room (fasteners must be 3/8" from edge and shall not penetrate more than 1/8")
05/05/2026 COT - HCBU - Framing Partial Pass 5/5/26: Drywall inspection for electrical rooms east wall (in rooms 276,376,476,576,676,776)
05/11/2026 COT - HCBU - Framing Partial Pass 5/11/26: DRYWALL NAILING FOR SHAFT #8 at 3rd and 4th floor approved for first layer.
05/12/2026 COT - HCBU - Framing Partial Pass 5/12/26: DRYWALL NAILING FOR SHAFT #8 at 3rd and 4th floor approved for second layer.
05/14/2026 COT - HCBU - Framing Partial Pass 5/14/2027 Nail Inspection for Shafts and Level 1 Unit Restrooms. 134,130,126,122,118 fire tape approved behind and to the side of shower walls.
05/15/2026 COT - HCBU - Framing Partial Pass Inter & Above ceiling 3rd floor rooms 362,359,360,358,356,354,352,353,350,351,348,346 approved. Okay to proceed progress areas. 5/15/2026
05/18/2026 COT - HCBU - Framing Partial Pass 5/18/26: shower wall fire taping rooms (134,136,138), shower walls 2nd floor screw inspection ( 212,214,216,218,220,222,224,226,228,230), MEP rooms 316,322,317,330,319, over notched studs require fix, code compliance nail plates required at plumbing walls
05/19/2026 COT - HCBU - Framing Partial Pass 5/19/26: drywall screw nailing behind shower walls 2nd floor fire tape approved at units 212-230, screw inspection approved in units 232-240. (Pending 218)
05/27/2026 COT - HCBU - Framing Partial Pass 5/27/26: Level 2 - 1st Layer Drywall for demising walls and corridor walls.
05/29/2026 COT - HCBU - Framing Partial Pass 5/29/26:MEP approved In rooms 462,460,459,471,458,456,454, 452,450,453,455,457,413
06/01/2026 COT - HCBU - Framing Partial Pass Partial pass 4th floor units 415,484,416,422,417,430,419,436,485,441,442 approved. Okay to proceed progress areas. 6/1/2026
06/03/2026 COT - HCBU - Framing Partial Pass 6/3/26: above ceiling MEP and framing approved In rooms (184,179.4,179.3,179.2,180,180.183,183A,178.1,178.2,178.3,178.4,178.5,178.6,)
06/05/2026 COT - HCBU - Framing Partial Pass 6/5/26: Drywall nailing approved at (112,114,116,118,120,122,124,126,128,130,132,136,138,188,187,186),electrical room 7th floor rooms 772,672,572,472,372, 773,573,373
06/08/2026 COT - HCBU - Framing Partial Pass 6/8/26: 3rd floor corridor approved and draft stop between partition walls.
06/09/2026 COT - HCBU - Framing Partial Pass 6/9/26: Shaft # 8 3rd-4th floor (fire tape), shaft (#4,5,6,7,8,9) 3rd-6th floor (fire tape), rooms (372,472,572,672,772,373,573,773) fire tape, elec room (376,476,576,676,776) 2nd layer, shaft # 4 and 5 floors 3-6
COT - HCBU - Framing Scheduled
12/29/2025 COT - HCBU - Framing Partial Pass Lecel #3, Section C decking . Ensure all straps are in place and sheathing edges are properly secured.