| 01/05/2026 |
COT - HCBU - Framing |
|
Partial Pass |
Metal stud framing on Level #2, Section C. |
| 01/07/2026 |
COT - HCBU - Framing |
|
Partial Pass |
Level #3; Section C decking. Sheathing and straps are in place. Ok to erect walls in progress areas. |
| 01/16/2026 |
COT - HCBU - Framing |
|
Partial Pass |
4th Floor Decking of West side of structure. Ok to frame in progress areas. |
| 01/22/2026 |
COT - HCBU - Framing |
|
Partial Pass |
Level #4 deck; Section A. Ok to frame walls in progress areas. |
| 01/26/2026 |
COT - HCBU - Framing |
|
Partial Pass |
Metal interior framing at Level #2; sections A & B. |
| 01/28/2026 |
COT - HCBU - Framing |
|
Partial Pass |
Level #4, Northeast portion of deck; straps are in place. Ok to frame walls in progress area. |
| 01/30/2026 |
COT - HCBU - Framing |
|
Partial Pass |
Level #5, section C deck. Straps are in place; Ok to construct walls in progress area. |
| 02/04/2026 |
COT - HCBU - Framing |
|
Partial Pass |
Level #5, Section C deck; strapping in place, nail pattern is correct. Ok to lay-out and erect walls. |
| 02/06/2026 |
COT - HCBU - Framing |
|
Partial Pass |
Exterior wall framing of West side of structure at levels #1 and #2. Ok to cover progress areas with sheathing. |
| 02/09/2026 |
COT - HCBU - Framing |
|
Partial Pass |
Level #1; Interior West side room units: metal framing. |
| 02/10/2026 |
COT - HCBU - Framing |
|
Partial Pass |
Level #2 West side room units interior metal framing. |
| 02/11/2026 |
COT - HCBU - Framing |
|
Partial Pass |
Level #5; Sections A, B, and C decking. Required straps and sheathing are in place. Ok to lay-out and erect interior walls. |
| 02/12/2026 |
COT - HCBU - Framing |
|
Partial Pass |
Level #2, East side room units; metal stud framing. Main lobby area and amenities rooms; metal stud framing. |
| 02/17/2026 |
COT - HCBU - Framing |
|
Canceled |
Canceled due to inclement weather. Will reschedule 18 February |
| 02/24/2026 |
COT - HCBU - Framing |
|
Partial Pass |
Level #3 shear walls and hold downs (SW #1, 2, 3, 6). Level #6 decking for Section B; straps in place. Ok to lay-out and construct walls. |
| 02/27/2026 |
COT - HCBU - Framing |
|
Partial Pass |
Level #6 decking; Ok to lay-out and erect walls and install straps. |
| 03/04/2026 |
COT - HCBU - Framing |
|
Partial Pass |
Level #7; decking. Straps in place in Section B. Ok to lay-out and erect walls. |
| 03/10/2026 |
COT - HCBU - Framing |
|
Partial Pass |
3/10/26: Deck nailing L7 Section approved. Ok to proceed. |
| 03/16/2026 |
COT - HCBU - Framing |
|
Partial Pass |
3/16/26: Nail Deck Inspection for Level 7 Floor Area B |
| 03/17/2026 |
COT - HCBU - Framing |
|
Partial Pass |
3/16/26: Nail Deck Inspection for Level 7 Floor Area B and Area A |
| 04/02/2026 |
COT - HCBU - Framing |
|
Partial Pass |
4/2/26: Exterior Framing for Lobby Area |
| 04/21/2026 |
COT - HCBU - Framing |
|
Partial Pass |
4/21/26: 1st layer gypsum board at shafts #5,6,7 approved from 3rd floor to 6th floor. Ok to proceed with 2nd layer |
| 04/29/2026 |
COT - HCBU - Framing |
|
Partial Pass |
4/29/26: interior shear walls approved at 7th floor units (715,755,754,752,753,750,751,748), first layer drywall in electrical rooms east wall only (276,376,476,576,676,767) |
| 05/01/2026 |
COT - HCBU - Framing |
|
Partial Pass |
5/1/26:Level 1 Units Nail Inspection for 1st Layer Drywall studios west room (fasteners must be 3/8" from edge and shall not penetrate more than 1/8") |
| 05/05/2026 |
COT - HCBU - Framing |
|
Partial Pass |
5/5/26: Drywall inspection for electrical rooms east wall (in rooms 276,376,476,576,676,776) |
| 05/11/2026 |
COT - HCBU - Framing |
|
Partial Pass |
5/11/26: DRYWALL NAILING FOR SHAFT #8 at 3rd and 4th floor approved for first layer. |
| 05/12/2026 |
COT - HCBU - Framing |
|
Partial Pass |
5/12/26: DRYWALL NAILING FOR SHAFT #8 at 3rd and 4th floor approved for second layer. |
| 05/14/2026 |
COT - HCBU - Framing |
|
Partial Pass |
5/14/2027 Nail Inspection for Shafts and Level 1 Unit Restrooms. 134,130,126,122,118 fire tape approved behind and to the side of shower walls. |
| 05/15/2026 |
COT - HCBU - Framing |
|
Partial Pass |
Inter & Above ceiling 3rd floor rooms 362,359,360,358,356,354,352,353,350,351,348,346 approved. Okay to proceed progress areas. 5/15/2026 |
| 05/18/2026 |
COT - HCBU - Framing |
|
Partial Pass |
5/18/26: shower wall fire taping rooms (134,136,138), shower walls 2nd floor screw inspection ( 212,214,216,218,220,222,224,226,228,230), MEP rooms 316,322,317,330,319, over notched studs require fix, code compliance nail plates required at plumbing walls |
| 05/19/2026 |
COT - HCBU - Framing |
|
Partial Pass |
5/19/26: drywall screw nailing behind shower walls 2nd floor fire tape approved at units 212-230, screw inspection approved in units 232-240. (Pending 218) |
| 05/27/2026 |
COT - HCBU - Framing |
|
Partial Pass |
5/27/26: Level 2 - 1st Layer Drywall for demising walls and corridor walls. |
| 05/29/2026 |
COT - HCBU - Framing |
|
Partial Pass |
5/29/26:MEP approved In rooms 462,460,459,471,458,456,454, 452,450,453,455,457,413 |
| 06/01/2026 |
COT - HCBU - Framing |
|
Partial Pass |
Partial pass 4th floor units 415,484,416,422,417,430,419,436,485,441,442 approved. Okay to proceed progress areas. 6/1/2026 |
| 06/03/2026 |
COT - HCBU - Framing |
|
Partial Pass |
6/3/26: above ceiling MEP and framing approved In rooms (184,179.4,179.3,179.2,180,180.183,183A,178.1,178.2,178.3,178.4,178.5,178.6,) |
| 06/05/2026 |
COT - HCBU - Framing |
|
Partial Pass |
6/5/26: Drywall nailing approved at (112,114,116,118,120,122,124,126,128,130,132,136,138,188,187,186),electrical room 7th floor rooms 772,672,572,472,372, 773,573,373 |
| 06/08/2026 |
COT - HCBU - Framing |
|
Partial Pass |
6/8/26: 3rd floor corridor approved and draft stop between partition walls. |
| 06/09/2026 |
COT - HCBU - Framing |
|
Partial Pass |
6/9/26: Shaft # 8 3rd-4th floor (fire tape), shaft (#4,5,6,7,8,9) 3rd-6th floor (fire tape), rooms (372,472,572,672,772,373,573,773) fire tape, elec room (376,476,576,676,776) 2nd layer, shaft # 4 and 5 floors 3-6 |
|
COT - HCBU - Framing |
|
Scheduled |
|
| 12/29/2025 |
COT - HCBU - Framing |
|
Partial Pass |
Lecel #3, Section C decking . Ensure all straps are in place and sheathing edges are properly secured. |