Inspection History Details
Inspection Status: Re-inspection required
Inspection History: COT - HCEL - Electrical Above Ceiling
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/01/2026 | COT - HCEL - Electrical Above Ceiling | Re-inspection required | 5.1.26: Hot water lines 3/4" and larger shall be properly insulated with minimum R3 insulation, properly support pex line and DWV throughout, dryer exhaust must be constructed of smooth material, kitchen hood shall be constructed of smooth materials, fire caulking required throughout at common walls, proper secure low voltage, back to back receptacles with inserts are required to have putty pad installed, provide Documentation on how large penetrations will be sealed, separate MC cable from copper lines, seal all penetrations (from low volt, mechanical, sprinkler, plumbing) | |
| 05/04/2026 | COT - HCEL - Electrical Above Ceiling | Re-inspection required | 5/4/26: putty pads at receptacle boxes shall not be over stretched as this will ruin the UL listing on product (1/8" thickness around boxes, all penetrations at top plates shall be fire caulked, draft stop required horizontally every 10' at common walls, nail plates required where MEP come within 1/4" from face of stud, over notched or over board top & bottom plates required structural strap and this strap shall extend 2" below and above the plates. Ensure all NM cable is secured off of gusset plates, damaged gusset plates on trusses required engineer fix. Smoke detectors required in each room and in the immediate vicinity outside of the rooms. Smoke detectors shall be no closer than 10' to kitchen range. | |
| 05/06/2026 | COT - HCEL - Electrical Above Ceiling | Partial Pass | 5/6/2026 MEP approved above ceilings 2nd floor units 212-240. Okay to proceed progress areas. | |
| 05/08/2026 | COT - HCEL - Electrical Above Ceiling | Partial Pass | 5/8/2026 MEP approved above ceilings 2nd floor units 262,259,260,258,256,254,255,252,253,250,251,257,213,215. Okay to proceed progress areas. | |
| 05/13/2026 | COT - HCEL - Electrical Above Ceiling | Partial Pass | 5/13/26:In-Wall and Above Inspection for Unit 112 | |
| 05/15/2026 | COT - HCEL - Electrical Above Ceiling | Partial Pass | Inter & Above ceiling 3rd floor rooms 362,359,360,358,356,354,352,353,350,351,348,346 approved. Okay to proceed progress areas. 5/15/2026 | |
| 05/18/2026 | COT - HCEL - Electrical Above Ceiling | Partial Pass | 5/18/26: shower wall fire taping rooms (134,136,138), shower walls 2nd floor screw inspection ( 212,214,216,218,220,222,224,226,228,230), MEP rooms 316,322,317,330,319, over notched studs require fix, code compliance nail plates required at plumbing walls | |
| 05/20/2026 | COT - HCEL - Electrical Above Ceiling | Partial Pass | 5/20/26: 3rd floor MEP in wall and above ceiling units 316,322,317,330,319,336,341,342,343,315,313,355,357) ok to proceed with progress areas. | |
| 05/29/2026 | COT - HCEL - Electrical Above Ceiling | Partial Pass | 5/29/26:MEP approved In rooms 462,460,459,471,458,456,454, 452,450,453,455,457,413 | |
| 06/01/2026 | COT - HCEL - Electrical Above Ceiling | Partial Pass | Partial pass 4th floor units 415,484,416,422,417,430,419,436,485,441,442 approved. Okay to proceed progress areas. 6/1/2026 | |
| 06/03/2026 | COT - HCEL - Electrical Above Ceiling | Partial Pass | 6/3/26: above ceiling MEP and framing approved In rooms (184,179.4,179.3,179.2,180,180.183,183A,178.1,178.2,178.3,178.4,178.5,178.6,) | |
| 06/04/2026 | COT - HCEL - Electrical Above Ceiling | Partial Pass | 6/4/26: MEP approval in rooms 446,448,451,443 Fastener spacing approval at 2nd layer behind tubs in rooms 251,250,252,253,255,257,260,259,213,215, Fire tape at areas behind tubs in rooms 254,256,258,262 |
|
| 06/08/2026 | COT - HCEL - Electrical Above Ceiling | Partial Pass | 6/8/26: 3rd floor corridor approved and draft stop between partition walls. | |
| 06/12/2026 | COT - HCEL - Electrical Above Ceiling | Partial Pass | 6/12/26: CORRIDOR 2ND FLOOR ABOVE CEILING MEP, IN WALL 2ND FLOOR (279,280.1,280.2,280.3,280.4,280.5,280.6), 5th floor (pvc,CPVC,pex rooms 557,513,555,516,515 pressure test approved), 6th floor pvc test (657,613,656,616,615), 7th floor pvc (756,713,756,716,715) | |
| 06/18/2026 | COT - HCEL - Electrical Above Ceiling | Partial Pass | ||
| 06/24/2026 | COT - HCEL - Electrical Above Ceiling | Partial Pass | Level 4 all corridors approved. Okay to proceed progress areas. 6/24/2026 | |
| 06/25/2026 | COT - HCEL - Electrical Above Ceiling | Partial Pass | Partial pass. MEP approved 5th floor units 516,513,515,557,555. 6/25/2026 | |
| 06/26/2026 | COT - HCEL - Electrical Above Ceiling | Partial Pass | Partial pass. MEP approved 5th floor units 554,552,553,550,551,548,546,543,542,541. 6/26/2026 | |
| 06/29/2026 | COT - HCEL - Electrical Above Ceiling | Partial Pass | 6/29/26: 5TH floor MEP Corridor and above ceiling and in wall. Interior shear-bracing 2nd floor corridor and shaft# |
|
| 07/02/2026 | COT - HCEL - Electrical Above Ceiling | Partial Pass | 7/2/2026 Partial pass. Lighting in place at Exterior garage soffit north east corner. MEP approved units 662,659,660,658,656,654,657,655,615,613. Okay to proceed progress areas. | |
| COT - HCEL - Electrical Above Ceiling | Scheduled |