| 01/15/2026 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
Electric underground: trenching for SES at Northeast area of structure; 2” - 3” conduit lines. Masonry pre-grout; P-1 storage room, topped out. Ok to grout progress area. |
| 01/21/2026 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
SES conduits to TEP main lines at Northeast corner of structure: 10@ 3” conduits, 1 @ 2” conduit line. Ok to cover progress ares of Electric underground. |
| 01/22/2026 |
COT - HCEL - Electrical Intermediate |
|
Not Ready |
Electric underground at Northeast area of structure. Will reschedule for 23 January. |
| 01/23/2026 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
Electric underground: SES lines connected to TEP main service lines at Northwest corner of structure. Ok to cover progress areas and cover adjacent alley way. |
| 01/28/2026 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
Level #1; in wall electric at Electric room, Maintenance room, Bike Storage, Pool Equipment room, video room. |
| 02/18/2026 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
Main entry and amenities rooms. In wall electric switches and receptacles. |
| 03/06/2026 |
COT - HCEL - Electrical Intermediate |
|
Re-inspection required |
3/6/26: 114,116,118,120,122 (re-inspection required) MC supports required throughout, grounding all metallic boxes, above ceiling electrical requires supports throughout |
| 03/27/2026 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
3/27/26: Partial electrical intermediate at all exterior walls at rooms 114,116,118,120122,124,126,128,130,132,134,136,138,140,251,250,252,255,254,256,258,260,259,262,257,213,215,212,214,216,218,220,222,224,226,228,230,232,234,236,238,240,253 |
| 09/11/2025 |
COT - HCEL - Electrical Intermediate |
|
Canceled |
Contractor cancelled, will reschedule for 12 September. |
| 09/12/2025 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
Electric underground ground conduits for primary lines to panel at GL: 8.5/E.5. Ok to cover progress area. |
| 10/02/2025 |
COT - HCEL - Electrical Intermediate |
|
Not Ready |
Contractor cancelled; will reschedule for 3 October. |
| 10/03/2025 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
Electric underground: 1” conduits at GL: 13/F.9 - D. OK to cover progress areas. |
| 10/09/2025 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
Electric conduits at 1 1/4 - 2” at Level #2 Podium at GL: 5 - 7.5/D.5 - A: SOG at 12 - 13/E.9 - A. |
| 10/23/2025 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
Level #1; in slab conduits (1” - 1 1/2”) at GL; 9/9 - 13/F.9 - E.9. |
| 11/06/2025 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
Electric in slab on grade at GL: 9 - 12/E.5 - D. OK to place concrete in progress area. |
| 11/24/2025 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
Parking garage Level #1; junction boxes and conduits in place throughout area. |
| 12/03/2025 |
COT - HCEL - Electrical Intermediate |
|
Partial Pass |
Electric underground at Southeast corner of structure; conduits 1” - 2 1/2”. Ok to cover approximately 45’ of trench. |