Inspection History Details
Inspection Status: Re-inspection required
Inspection History: COT - HCBU - Building Above Ceiling
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 05/01/2026 | COT - HCBU - Building Above Ceiling | Re-inspection required | 5.1.26: Hot water lines 3/4" and larger shall be properly insulated with minimum R3 insulation, properly support pex line and DWV throughout, dryer exhaust must be constructed of smooth material, kitchen hood shall be constructed of smooth materials, fire caulking required throughout at common walls, proper secure low voltage, back to back receptacles with inserts are required to have putty pad installed, provide Documentation on how large penetrations will be sealed, separate MC cable from copper lines, seal all penetrations (from low volt, mechanical, sprinkler, plumbing) | |
| 05/05/2026 | COT - HCBU - Building Above Ceiling | Partial Pass | 5/5/26: M.E.P APPROVED ABOVE CEILING IN STUDIO UNITS 1ST FLOOR (112,114,116,118,120,122,124,126,128,130,132,134,136,138,140) | |
| 05/06/2026 | COT - HCBU - Building Above Ceiling | Partial Pass | 5/6/2026 MEP approved above ceilings 2nd floor units 212-240. Okay to proceed progress areas. | |
| 05/08/2026 | COT - HCBU - Building Above Ceiling | Partial Pass | 5/8/2026 MEP approved above ceilings 2nd floor units 262,259,260,258,256,254,255,252,253,250,251,257,213,215. Okay to proceed progress areas. | |
| 05/13/2026 | COT - HCBU - Building Above Ceiling | Partial Pass | 5/13/26:In-Wall and Above Inspection for Unit 112 | |
| 05/15/2026 | COT - HCBU - Building Above Ceiling | Partial Pass | Inter & Above ceiling 3rd floor rooms 362,359,360,358,356,354,352,353,350,351,348,346 approved. Okay to proceed progress areas. 5/15/2026 | |
| 05/18/2026 | COT - HCBU - Building Above Ceiling | Partial Pass | 5/18/26: shower wall fire taping rooms (134,136,138), shower walls 2nd floor screw inspection ( 212,214,216,218,220,222,224,226,228,230), MEP rooms 316,322,317,330,319, over notched studs require fix, code compliance nail plates required at plumbing walls | |
| 05/29/2026 | COT - HCBU - Building Above Ceiling | Partial Pass | 5/29/26:MEP approved In rooms 462,460,459,471,458,456,454, 452,450,453,455,457,413 | |
| 06/01/2026 | COT - HCBU - Building Above Ceiling | Partial Pass | Partial pass 4th floor units 415,484,416,422,417,430,419,436,485,441,442 approved. Okay to proceed progress areas. 6/1/2026 | |
| 06/03/2026 | COT - HCBU - Building Above Ceiling | Partial Pass | 6/3/26: above ceiling MEP and framing approved In rooms (184,179.4,179.3,179.2,180,180.183,183A,178.1,178.2,178.3,178.4,178.5,178.6,) | |
| 06/04/2026 | COT - HCBU - Building Above Ceiling | Partial Pass | 6/4/26: MEP approval in rooms 446,448,451,443 Fastener spacing approval at 2nd layer behind tubs in rooms 251,250,252,253,255,257,260,259,213,215, Fire tape at areas behind tubs in rooms 254,256,258,262 |
|
| 06/08/2026 | COT - HCBU - Building Above Ceiling | Partial Pass | 6/8/26: 3rd floor corridor approved and draft stop between partition walls. |