Inspection History Details
Inspection Status: Not Ready
Inspection History: COT - HCPL - Plumbing Intermediate
| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/11/2026 | COT - HCPL - Plumbing Intermediate | Not Ready | ||
| 06/15/2026 | COT - HCPL - Plumbing Intermediate | Not Ready | ||
| 06/16/2026 | COT - HCPL - Plumbing Intermediate | Not Ready | ||
| 06/18/2026 | COT - HCPL - Plumbing Intermediate | Not Ready | ||
| 06/24/2026 | COT - HCPL - Plumbing Intermediate | Not Ready | ||
| 06/29/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | ||
| 07/01/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | ||
| 07/06/2026 | COT - HCPL - Plumbing Intermediate | Not Ready | Cancel by contractor | |
| 07/07/2026 | COT - HCPL - Plumbing Intermediate | Not Ready | ||
| 07/08/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | ||
| 07/10/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | ||
| 07/14/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | ||
| 07/17/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | ||
| 07/20/2026 | COT - HCPL - Plumbing Intermediate | Not Ready | ||
| 07/21/2026 | COT - HCPL - Plumbing Intermediate | Not Ready | ||
| 07/22/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 7/22/26: MEP APPROVED WEST WING 14TH FLOOR | |
| 07/27/2026 | COT - HCPL - Plumbing Intermediate | Not Ready | ||
| 07/28/2026 | COT - HCPL - Plumbing Intermediate | Re-inspection required | 7/28/26: MEP WALKED IN UNITS 1421,1422,1423,1424,1426 (findings: DWV required to have riser clamps, DWV required supports 4' o.c at horizontal runs, DWV 2" requires supports midway, nail plates required where plumbing comes closer than 1 1/4" to face of stud, low voltage must be installed and properly supported throughout, MC cables require supports midway 12" from boxes, multiple receptacles buried behind drywall. All units must be clean for inspection, penetration at floors must be sealed, duct must be appropriately sealed) | |
| 07/29/2026 | COT - HCPL - Plumbing Intermediate | Not Ready | ||
| 07/30/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | ||
| 07/31/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 7/31/2026 Partial pass. 14th floor MEP and above ceiling inspection units 1420, 1419, 1418, electrical room drywall approved. 1415. | |
| 08/04/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | ||
| 08/07/2026 | COT - HCPL - Plumbing Intermediate | Re-inspection required | 8/7/2026 DWV not under test. Shower pans/tubs still need to be tested. 8/7/2026 16th floor unit 1601 Bang plates 1x walls Strap hvac flex every 4ft Bang plates hvac line set Resecure strap hvac exhaust kitchen 1602 Finish electric at entry Frame exhaust bath Outlet farther than 6ft from bedroom door Strap duct 4ft Tear in duct 1603 Outlet needed 2ft from bedroom door Outlet in bedroom over 12ft 1604 Bang plates 1x walls in closet mc cable Remove cut mc at bathroom wall Move Outlet in kitchen 1605 Mc bang plates bedroom and entry Cut plumbing stack kitchen 1606 Move outlet kitchen Bang plates 1x walls mc Strap mc bathroom light 1607 Mc bang plates bedroom 1x walls |
|
| 08/11/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 8.11.26 1601-1613 all corrections made okay to Sheetrock |
|
| 08/13/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | ||
| 08/17/2026 | COT - HCPL - Plumbing Intermediate | Partial Pass | 8/17/26: MEP RE-WALK APPROVED IN ROOMS 1615,1616,1617,1620,1621,1622,1623,1625,1626. |