Permit: TC-COM-0624-01123

Parcel: 115180220


Addresses:

1501 N ORACLE RD

Inspection Status: Not Ready

Inspection History: COT - HCBU - Framing

Date Description Inspector Results Comments
06/11/2026 COT - HCBU - Framing Not Ready
06/15/2026 COT - HCBU - Framing Not Ready
06/16/2026 COT - HCBU - Framing Not Ready
06/18/2026 COT - HCBU - Framing Not Ready
06/23/2026 COT - HCBU - Framing Partial Pass
06/24/2026 COT - HCBU - Framing Not Ready
06/25/2026 COT - HCBU - Framing Not Ready
06/29/2026 COT - HCBU - Framing Partial Pass
07/06/2026 COT - HCBU - Framing Not Ready Canceled by contractor
07/07/2026 COT - HCBU - Framing Not Ready
07/08/2026 COT - HCBU - Framing Partial Pass
07/10/2026 COT - HCBU - Framing Partial Pass
07/15/2026 COT - HCBU - Framing Partial Pass
07/17/2026 COT - HCBU - Framing Partial Pass
07/20/2026 COT - HCBU - Framing Not Ready
07/21/2026 COT - HCBU - Framing Not Ready
07/22/2026 COT - HCBU - Framing Partial Pass 7/22/26: MEP APPROVED WEST WING 14TH FLOOR
07/28/2026 COT - HCBU - Framing Re-inspection required 7/28/26: MEP WALKED IN UNITS 1421,1422,1423,1424,1426 (findings: DWV required to have riser clamps, DWV required supports 4' o.c at horizontal runs, DWV 2" requires supports midway, nail plates required where plumbing comes closer than 1 1/4" to face of stud, low voltage must be installed and properly supported throughout, MC cables require supports midway 12" from boxes, multiple receptacles buried behind drywall. All units must be clean for inspection, penetration at floors must be sealed, duct must be appropriately sealed)
07/29/2026 COT - HCBU - Framing Not Ready
07/30/2026 COT - HCBU - Framing Partial Pass
07/31/2026 COT - HCBU - Framing Partial Pass 7/31/2026 Partial pass. 14th floor MEP and above ceiling inspection units 1420, 1419, 1418, electrical room drywall approved. 1415.
08/03/2026 COT - HCBU - Framing Partial Pass 8/3/2026 per previous notes.
08/04/2026 COT - HCBU - Framing Partial Pass
08/07/2026 COT - HCBU - Framing Re-inspection required 8/7/2026 DWV not under test. Shower pans/tubs still need to be tested. 8/7/2026 16th floor unit 1601
Bang plates 1x walls
Strap hvac flex every 4ft
Bang plates hvac line set
Resecure strap hvac exhaust kitchen
1602
Finish electric at entry
Frame exhaust bath
Outlet farther than 6ft from bedroom door
Strap duct 4ft
Tear in duct
1603
Outlet needed 2ft from bedroom door
Outlet in bedroom over 12ft
1604
Bang plates 1x walls in closet mc cable
Remove cut mc at bathroom wall
Move Outlet in kitchen
1605
Mc bang plates bedroom and entry
Cut plumbing stack kitchen
1606
Move outlet kitchen
Bang plates 1x walls mc
Strap mc bathroom light
1607
Mc bang plates bedroom 1x walls
08/13/2026 COT - HCBU - Framing Partial Pass
08/17/2026 COT - HCBU - Framing Partial Pass 8/17/26: MEP RE-WALK APPROVED IN ROOMS 1615,1616,1617,1620,1621,1622,1623,1625,1626.