Permit: TC-COM-0624-01123

Parcel: 115180220


Addresses:

1501 N ORACLE RD

Inspection Status: Not Ready

Inspection History: COT - HCME - Mechanical Final 

Date Description Inspector Results Comments
10/01/2026 COT - HCME - Mechanical Final  Not Ready
10/02/2026 COT - HCME - Mechanical Final  Partial Pass
10/07/2026 COT - HCME - Mechanical Final  Partial Pass
10/08/2026 COT - HCME - Mechanical Final  Partial Pass
10/09/2026 COT - HCME - Mechanical Final  Not Ready
10/14/2026 COT - HCME - Mechanical Final  Partial Pass 10/14/26: Okay to apply for level 4 TCO (Floor 15) - pending Fire and Water Sterilization Report.
10/26/2026 COT - HCME - Mechanical Final  Partial Pass 10/26/2026 Partial pass. 14th floor Units 1403, 1404, 1405, 1406 (pending vertical grab bar in roll in shower), 1407, 1408, 1409, 1411 (pending vertical grab bar in roll in shower. Flush valve shall be on the open end). All other units approved.
10/27/2026 COT - HCME - Mechanical Final  Partial Pass
11/02/2026 COT - HCME - Mechanical Final  Partial Pass 11/2/2026 Partial pass. 1419,1418,1416,1415, corrections were made. 1420,1421,1422,1423,1424,1425,1426,1414 units approved.
11/04/2026 COT - HCME - Mechanical Final  Re-inspection required 11/4/26: 14th floor corridor + electrical/storage rooms final walk:
Existing Electrical room -
1. Identify Romex line in existing panel
2. Mark existing electrical panel schedule

West mechanical room -
1. Clamps on unistrut above fan coil
2. HVAC refrigerant line supports
3. Conduit supports
4. Verify and label breaker for disconnect
5. Tie in overflow switch on fan coil

IDF room -
1. Supports on conduits within 3'
2. Remove low voltage from fire sprinkler pipe

Elevator lobby Electrical -
1. Mc clamps
2. Mark electrical panel
3. Clamps off of light

Janitors closet -
1. Clamp temporary water lines

East Main Electrical room -
1. MC clamps
2. Verify disconnect
3. Remove unused conduit

East Existing Electrical room -
1. Replace knockouts on box
2. Relabel panel schedule
11/05/2026 COT - HCME - Mechanical Final  Partial Pass
11/10/2026 COT - HCME - Mechanical Final  Not Ready
11/13/2026 COT - HCME - Mechanical Final  Partial Pass
11/17/2026 COT - HCME - Mechanical Final  Partial Pass
11/20/2026 COT - HCME - Mechanical Final  Partial Pass Common areas and corridors 16th floor approved. 11/20/2026