| Date | Description | Inspector | Results | Comments |
|---|---|---|---|---|
| 06/18/2026 | COT - LCPL - Plumbing Final | Re-inspection required | 6/18/26: ADA REQUIREMENTS must be met at 8 units per IBC 1108.6.1.1, electrical outlets required throughout per IEBC 1007.4, anti-tip must be properly installed at every unit, properly secure. NM-cable at counter, listed cover required at j-box. | |
| 08/03/2026 | COT - LCPL - Plumbing Final | Not Ready | Building 5. Unit 109. Remove door from closet with sub panel. Complete panel schedule at sub panel. Add receptacle due to spacing over 12’. Coat hanger shall be at 48”. Mirror shall be at 40” to the reflective side. Ensure all flush valves are on the open side at all ADA bathrooms. Unit 100 missing receptacle near door entry. Lav greater than 34” coat hanger shall be at 48”. Mirror shall be at 40” Receptacle near kitchen counter shall be GFCI protected. Remove pan head screws from sub panel covers. |
|
| 08/18/2026 | COT - LCPL - Plumbing Final | Partial Pass | 8/18/2026 Building 5. 101,103,105,107, all corrections were made in laundry room, 109,111,115,117,119,121,123,125. |